Green extension of time (green EOT): a framework for environmental compliance delay under FIDIC construction contracts

Mandatory environmental compliance obligations increasingly affect construction programmes. Under FIDIC-based contracts, Extension of Time (EOT) mechanisms, including the Changes in Laws mechanism in Sub-Clause 13.6, are triggered by identifiable contractual or regulatory events. They leave ambiguous a narrow category of delay arising from intensified enforcement of an unchanged permit condition or statutory standard, and from generally applicable statutory duties triggered by factual circumstances without any new regulatory act, exposing contractors to sanctions for delays that may be unavoidable. Using a normative legal research methodology, this article advances the Green Extension of Time (Green EOT) as a compliance-based time entitlement operating alongside existing FIDIC mechanisms. It makes three contributions. First, it identifies a compliance-driven delay category not expressly captured by Sub-Clause 13.6. Second, it develops a Four-Limb Test (legal compulsion, unforeseeability at Base Date, critical path impact, and reasonable mitigation) as an operational eligibility standard. Third, it integrates this category into critical path method (CPM) delay analysis and dispute board practice, supported by a model Particular Condition and illustrated through representative examples rather than claims of systemic occurrence. The framework situates environmental compliance delay within construction management practice rather than purely doctrinal analysis.

Authors

Institutions

Publication Details

Journal
Construction Management and Economics
Published
2026-10-29
DOI
https://doi.org/10.1080/01446193.2026.2752185
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Green extension of time (green EOT): a framework for environmental compliance delay under FIDIC construction contracts

John Haris Pardomuan Girsang
1 links
Construction Management and Economics
Construction Project Management and Performance
article

Green extension of time (green EOT): a framework for environmental compliance delay under FIDIC construction contracts

John Haris Pardomuan Girsang
article en

Abstract

Mandatory environmental compliance obligations increasingly affect construction programmes. Under FIDIC-based contracts, Extension of Time (EOT) mechanisms, including the Changes in Laws mechanism in Sub-Clause 13.6, are triggered by identifiable contractual or regulatory events. They leave ambiguous a narrow category of delay arising from intensified enforcement of an unchanged permit condition or statutory standard, and from generally applicable statutory duties triggered by factual circumstances without any new regulatory act, exposing contractors to sanctions for delays that may be unavoidable. Using a normative legal research methodology, this article advances the Green Extension of Time (Green EOT) as a compliance-based time entitlement operating alongside existing FIDIC mechanisms. It makes three contributions. First, it identifies a compliance-driven delay category not expressly captured by Sub-Clause 13.6. Second, it develops a Four-Limb Test (legal compulsion, unforeseeability at Base Date, critical path impact, and reasonable mitigation) as an operational eligibility standard. Third, it integrates this category into critical path method (CPM) delay analysis and dispute board practice, supported by a model Particular Condition and illustrated through representative examples rather than claims of systemic occurrence. The framework situates environmental compliance delay within construction management practice rather than purely doctrinal analysis.

Construction Management and Economics
Universitas Pekalongan (ID)
Openalex Percentile: Top 10%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon