PhysBridge: Response-supervised grid pretraining with physics-constrained local correction for transferable power-system intelligence

Operating modern power grids requires coordinated solutions for optimal dispatch, state estimation, price prediction, and contingency analysis, yet these tasks are usually modeled separately. We present PhysBridge, a response-oriented pretraining framework in which historical windows provide context while solver-generated perturbation responses, active constraints, and local sensitivities define the pretraining targets. PhysBridge combines a temporal-graph encoder with a Primal-Dual Response Bridge (PDR-Bridge) that performs safeguarded local refinement and outputs transferable primal, projection-dual, sensitivity, and health tokens. Across IEEE 14-, 30-, 57-, 118-, and 300-bus systems, the benchmark contains 26.3 million solver-generated perturbation-response pairs; in the 300-bus transfer setting, pretraining uses only the 21.04 million nominal pairs from the 14-, 30-, 57-, and 118-bus source topologies. Across three runs on unseen IEEE 300-bus transfer with 10% labels, PhysBridge obtains a 2.21±0.05% OPF cost gap, 96.3±0.2% feasibility, 1.84±0.05 $/MWh LMP MAE, and 91.6±0.3% contingency/fault event macro F1. Relative to a matched rollout-only model trained on the same source corpus without response targets or bridge refinement, these values correspond to a 50.8% lower OPF gap and a 7.4 percentage-point higher event F1. The bridge requires 12.4 ms per 300-bus forward pass and activates fallback on 4.6% of stressed windows. Comparisons with supervised-only OPF specialists that do not receive matched solver-generated pretraining are interpreted as task-relevant performance under the proposed pretraining regime, not as architecture-only superiority.

Authors

Institutions

Publication Details

Journal
PLoS ONE
Published
2026-10-28
DOI
https://doi.org/10.1371/journal.pone.0359953
Primary Topic
Electric Power System Optimization
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PhysBridge: Response-supervised grid pretraining with physics-constrained local correction for transferable power-system intelligence

Donglan Liu, Shanjie Xu, Yuhui Jin, Honglei YAO et al.
PLoS ONE
Electric Power System Optimization
article

PhysBridge: Response-supervised grid pretraining with physics-constrained local correction for transferable power-system intelligence

Donglan Liu, Shanjie Xu, Yuhui Jin, Honglei YAO, Qinguo Liu
article en

Abstract

Operating modern power grids requires coordinated solutions for optimal dispatch, state estimation, price prediction, and contingency analysis, yet these tasks are usually modeled separately. We present PhysBridge, a response-oriented pretraining framework in which historical windows provide context while solver-generated perturbation responses, active constraints, and local sensitivities define the pretraining targets. PhysBridge combines a temporal-graph encoder with a Primal-Dual Response Bridge (PDR-Bridge) that performs safeguarded local refinement and outputs transferable primal, projection-dual, sensitivity, and health tokens. Across IEEE 14-, 30-, 57-, 118-, and 300-bus systems, the benchmark contains 26.3 million solver-generated perturbation-response pairs; in the 300-bus transfer setting, pretraining uses only the 21.04 million nominal pairs from the 14-, 30-, 57-, and 118-bus source topologies. Across three runs on unseen IEEE 300-bus transfer with 10% labels, PhysBridge obtains a 2.21±0.05% OPF cost gap, 96.3±0.2% feasibility, 1.84±0.05 $/MWh LMP MAE, and 91.6±0.3% contingency/fault event macro F1. Relative to a matched rollout-only model trained on the same source corpus without response targets or bridge refinement, these values correspond to a 50.8% lower OPF gap and a 7.4 percentage-point higher event F1. The bridge requires 12.4 ms per 300-bus forward pass and activates fallback on 4.6% of stressed windows. Comparisons with supervised-only OPF specialists that do not receive matched solver-generated pretraining are interpreted as task-relevant performance under the proposed pretraining regime, not as architecture-only superiority.

PLoS ONEVol. 21(10)
State Grid Shandong Electric Power Company (China) (CN)
Science and Technology Project of State Grid, State Grid Shandong Electric Power Company
Affordable and clean energy, Industry, innovation and infrastructure
Openalex Percentile: Top 24%
Electric Power System Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Laika access coming soon