Risk Governance for EPC Contracts with Startup Owners: An Integrated MCDM–Behavioral Framework

Large-scale international Engineering, Procurement, and Construction (EPC) projects undertaken for startup owners involve substantial transactional and financial risks that may not be adequately captured by conventional Failure Mode and Effects Analysis (FMEA), which assumes equal weighting of risk factors and rational decision-making. This study develops an integrated risk assessment framework combining the Modified Delphi Method (MDM), Step-wise Weight Assessment Ratio Analysis (SWARA), FMEA, Prospect Theory, and Decision-Making Trial and Evaluation Laboratory (DEMATEL) to identify, weight, behaviorally adjust, and analyze the causal relationships among EPC risks. A large international EPC turnkey project was examined using assessments from seven senior managers, resulting in 25 risk indicators across five dimensions. The results show that severity is the most influential risk factor, accounting for 43.5% of the total weight. Incorporating a prospect-theoretic transformation of the expert ratings alters conventional risk rankings, with owner insolvency, funding-chain disruptions, and liability-cap risks emerging among the nine most critical risks. DEMATEL further identifies Owner Relationship Risk and Contractual Risk as the primary causal dimensions, whereas Financial Risk represents the major outcome dimension. Sensitivity analyses of the criterion weights, prospect-theory parameters and reference point, together with expert-level bootstrapping, indicate that the high-priority risk set is robust, although the exact order within it is less certain. The proposed framework integrates behavioral preferences into EPC risk assessment; because it was validated retrospectively on a completed project, it is proposed as a basis for risk prioritization and bid-stage governance in future prospective applications.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-10-19
DOI
https://doi.org/10.3390/buildings16204123
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Governance for EPC Contracts with Startup Owners: An Integrated MCDM–Behavioral Framework

James J.H. Liou, Ching-Feng Lee
Buildings
Construction Project Management and Performance
article

Risk Governance for EPC Contracts with Startup Owners: An Integrated MCDM–Behavioral Framework

James J.H. Liou, Ching-Feng Lee
article en

Abstract

Large-scale international Engineering, Procurement, and Construction (EPC) projects undertaken for startup owners involve substantial transactional and financial risks that may not be adequately captured by conventional Failure Mode and Effects Analysis (FMEA), which assumes equal weighting of risk factors and rational decision-making. This study develops an integrated risk assessment framework combining the Modified Delphi Method (MDM), Step-wise Weight Assessment Ratio Analysis (SWARA), FMEA, Prospect Theory, and Decision-Making Trial and Evaluation Laboratory (DEMATEL) to identify, weight, behaviorally adjust, and analyze the causal relationships among EPC risks. A large international EPC turnkey project was examined using assessments from seven senior managers, resulting in 25 risk indicators across five dimensions. The results show that severity is the most influential risk factor, accounting for 43.5% of the total weight. Incorporating a prospect-theoretic transformation of the expert ratings alters conventional risk rankings, with owner insolvency, funding-chain disruptions, and liability-cap risks emerging among the nine most critical risks. DEMATEL further identifies Owner Relationship Risk and Contractual Risk as the primary causal dimensions, whereas Financial Risk represents the major outcome dimension. Sensitivity analyses of the criterion weights, prospect-theory parameters and reference point, together with expert-level bootstrapping, indicate that the high-priority risk set is robust, although the exact order within it is less certain. The proposed framework integrates behavioral preferences into EPC risk assessment; because it was validated retrospectively on a completed project, it is proposed as a basis for risk prioritization and bid-stage governance in future prospective applications.

BuildingsVol. 16(20)
National Taipei University of Technology (TW)
Openalex Percentile: Top 9%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.