Locational Assessment of Feasible Connection Capacity Ranges for AI Inference Data Centers in Distribution Networks with Photovoltaics

This study evaluates location-dependent feasible connection capacity intervals for AI inference data centers in a distribution network with photovoltaics. A synthetic 24-hour facility load profile is constructed from public inference request traces, measured processor power characteristics, and power usage effectiveness data. OpenDSS simulations assess 53 candidate buses under three line current limits. In the identified intervals, existing overvoltage determines the lower bounds, while undervoltage or line current constraints determine the upper bounds. The maximum interval width increases from 1.141 MW at 350 A to 1.938 MW at 450 A. Sites selected by the upper-bound and interval-width criteria differ under all three conditions. The results support joint assessment of capacity bounds, interval width, and limiting constraints when planning data center location and size under a fixed load profile.

Authors

Publication Details

Journal
The Transactions of The Korean Institute of Electrical Engineers
Published
2026-10-15
DOI
https://doi.org/10.5370/kiee.2026.75.10.2743
Primary Topic
Optimal Power Flow Distribution
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Locational Assessment of Feasible Connection Capacity Ranges for AI Inference Data Centers in Distribution Networks with Photovoltaics

Dong‐il Cho, Yun-Jin Cho, Won-Sik Moon, Jun-Hyuk Nam et al.
The Transactions of The Korean Institute of Electrical Engineers
Optimal Power Flow Distribution
article

Locational Assessment of Feasible Connection Capacity Ranges for AI Inference Data Centers in Distribution Networks with Photovoltaics

Dong‐il Cho, Yun-Jin Cho, Won-Sik Moon, Jun-Hyuk Nam, Min-Chan Kang
article en

Abstract

This study evaluates location-dependent feasible connection capacity intervals for AI inference data centers in a distribution network with photovoltaics. A synthetic 24-hour facility load profile is constructed from public inference request traces, measured processor power characteristics, and power usage effectiveness data. OpenDSS simulations assess 53 candidate buses under three line current limits. In the identified intervals, existing overvoltage determines the lower bounds, while undervoltage or line current constraints determine the upper bounds. The maximum interval width increases from 1.141 MW at 350 A to 1.938 MW at 450 A. Sites selected by the upper-bound and interval-width criteria differ under all three conditions. The results support joint assessment of capacity bounds, interval width, and limiting constraints when planning data center location and size under a fixed load profile.

The Transactions of The Korean Institute of Electrical EngineersVol. 75(10)
Industry, innovation and infrastructure, Affordable and clean energy, Climate action
Openalex Percentile: Top 24%
Optimal Power Flow Distribution
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.