Oracle of Bids: Preaward Bid Dispersion as an Early Warning Signal of Schedule Delays in Infrastructure Projects

Abstract Schedule delays in public infrastructure projects frequently result in liquidated damages (LD), yet most early warning tools rely on postaward information, limiting opportunities for prevention. This study proposes a preaward early warning framework that uses bid-stage dispersion as a market-generated signal of latent project uncertainty. Drawing on collective-intelligence and procurement-economics perspectives, the study tests whether dispersion among submitted bids is associated with LD outcomes using a manually constructed data set of 642 projects awarded by a US state transportation agency between 2015 and 2020. The analysis is associational and intended for preaward risk screening rather than causal inference. A logistic-regression model using only preaward information demonstrates meaningful discriminatory performance, indicating that projects incurring LD are systematically ranked higher in predicted risk at bid opening. Among dispersion measures, interquartile-range (IQR) dispersion exhibits the most persistent association with LD risk and remains nonzero under highly restrictive specifications that absorb county and award-year effects and apply regularization. Grouped cross-validation shows that predictive performance remains stable across counties and award years, with only modest attenuation under strict spatial and temporal hold-out. Robustness checks confirm that results are not driven by outliers or heavy-tailed LD severity. The findings indicate that bid dispersion‍—particularly central-mass disagreement captured by IQR—provides a low-burden, preaward early warning signal of schedule-delay risk. Because bid distributions are already available in modern e-procurement systems, dispersion-based analytics can be readily integrated into procurement workflows to support early screening, targeted review, and proactive oversight planning.

Authors

Publication Details

Journal
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Published
2026-10-14
DOI
https://doi.org/10.1061/jladah.ladr-1678
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Oracle of Bids: Preaward Bid Dispersion as an Early Warning Signal of Schedule Delays in Infrastructure Projects

Young Joo Kim
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Construction Project Management and Performance
article

Oracle of Bids: Preaward Bid Dispersion as an Early Warning Signal of Schedule Delays in Infrastructure Projects

Young Joo Kim
article en

Abstract

Abstract Schedule delays in public infrastructure projects frequently result in liquidated damages (LD), yet most early warning tools rely on postaward information, limiting opportunities for prevention. This study proposes a preaward early warning framework that uses bid-stage dispersion as a market-generated signal of latent project uncertainty. Drawing on collective-intelligence and procurement-economics perspectives, the study tests whether dispersion among submitted bids is associated with LD outcomes using a manually constructed data set of 642 projects awarded by a US state transportation agency between 2015 and 2020. The analysis is associational and intended for preaward risk screening rather than causal inference. A logistic-regression model using only preaward information demonstrates meaningful discriminatory performance, indicating that projects incurring LD are systematically ranked higher in predicted risk at bid opening. Among dispersion measures, interquartile-range (IQR) dispersion exhibits the most persistent association with LD risk and remains nonzero under highly restrictive specifications that absorb county and award-year effects and apply regularization. Grouped cross-validation shows that predictive performance remains stable across counties and award years, with only modest attenuation under strict spatial and temporal hold-out. Robustness checks confirm that results are not driven by outliers or heavy-tailed LD severity. The findings indicate that bid dispersion‍—particularly central-mass disagreement captured by IQR—provides a low-burden, preaward early warning signal of schedule-delay risk. Because bid distributions are already available in modern e-procurement systems, dispersion-based analytics can be readily integrated into procurement workflows to support early screening, targeted review, and proactive oversight planning.

Journal of Legal Affairs and Dispute Resolution in Engineering and ConstructionVol. 19(1)
Industry, innovation and infrastructure
Openalex Percentile: Top 10%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.