Evaluating the Construction Time Performance of Modern Methods of Construction in a House Building Experiment †

The potential of Modern Methods of Construction (MMCs) to tackle housing shortages while stimulating economies is often considered an effective means to contribute to the resolution of those two issues. This is reflected in house-building policies, largely due to assertions by scholars and regulators that MMCs can be economically effective and efficient, while improving the health and safety conditions of work. Though commentary on the theoretical advantages of MMCs exists, arguing the degree of their superior overall time performance, the literature lacks empirical substantiation of the construction time efficiencies of multiple MMCs in a live house construction experiment, administered by one construction company on a project site with equivalent specifications. This research gap is fulfilled to a degree by presenting an analysis of the construction time efficiency of four MMCs, including steel- and timber-based modular systems, and steel- and concrete-based panelized MMCs. The methodological framework includes analyses of project programs and designs, and staff interviews. The MMCs generated greater construction time inefficiencies than the traditionally built houses. The planned construction time performance of panelized construction was inferior to that of the modular methods. Inadequate site logistics and design issues were the main barriers to achieving the planned time efficiencies.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-10-13
DOI
https://doi.org/10.3390/buildings16204032
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluating the Construction Time Performance of Modern Methods of Construction in a House Building Experiment †

Vasil Angelov Atanasov
Buildings
BIM and Construction Integration
article

Evaluating the Construction Time Performance of Modern Methods of Construction in a House Building Experiment †

Vasil Angelov Atanasov
article en

Abstract

The potential of Modern Methods of Construction (MMCs) to tackle housing shortages while stimulating economies is often considered an effective means to contribute to the resolution of those two issues. This is reflected in house-building policies, largely due to assertions by scholars and regulators that MMCs can be economically effective and efficient, while improving the health and safety conditions of work. Though commentary on the theoretical advantages of MMCs exists, arguing the degree of their superior overall time performance, the literature lacks empirical substantiation of the construction time efficiencies of multiple MMCs in a live house construction experiment, administered by one construction company on a project site with equivalent specifications. This research gap is fulfilled to a degree by presenting an analysis of the construction time efficiency of four MMCs, including steel- and timber-based modular systems, and steel- and concrete-based panelized MMCs. The methodological framework includes analyses of project programs and designs, and staff interviews. The MMCs generated greater construction time inefficiencies than the traditionally built houses. The planned construction time performance of panelized construction was inferior to that of the modular methods. Inadequate site logistics and design issues were the main barriers to achieving the planned time efficiencies.

BuildingsVol. 16(20)
Robert Gordon University (GB)
Openalex Percentile: Top 16%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.