Optimal Configuration of Traction Power Supply Systems Based on Deep Reinforcement Learning

To address the coupling among power supply topology, module selection, capacity allocation, and N-2 contingency assessment in flexible traction power supply systems, a deep-reinforcement-learning-guided branch-and-bound method is proposed for equipment siting and sizing. The Actor network selects preferred branching actions, whereas the Critic network ranks search nodes; exact bound-based pruning and N-2 verification remain governed by the underlying branch-and-bound procedure. A feasibility-preservation result shows that any reported solution satisfies the prescribed N-2 capacity-support condition. Case study results show that the proposed method reduces the power deficit to zero under typical N-2 contingencies by establishing a medium-voltage DC through-feeding section and flexible interconnection channels. Compared with the reference case, the main configuration cost increases by 12.5%, indicating that the proposed method can enhance the system’s support capability under severe contingencies at the expense of a moderate increase in configuration cost.

Authors

Institutions

Publication Details

Journal
Applied System Innovation
Published
2026-08-27
DOI
https://doi.org/10.3390/asi9090176
Primary Topic
Railway Systems and Energy Efficiency
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimal Configuration of Traction Power Supply Systems Based on Deep Reinforcement Learning

Chongbo Sun, Zhiwei Wan, Kai Yuan, Yudi Ding et al.
Applied System Innovation
Railway Systems and Energy Efficiency
article

Optimal Configuration of Traction Power Supply Systems Based on Deep Reinforcement Learning

Chongbo Sun, Zhiwei Wan, Kai Yuan, Yudi Ding, Ming Nie, Yi Song
article en

Abstract

To address the coupling among power supply topology, module selection, capacity allocation, and N-2 contingency assessment in flexible traction power supply systems, a deep-reinforcement-learning-guided branch-and-bound method is proposed for equipment siting and sizing. The Actor network selects preferred branching actions, whereas the Critic network ranks search nodes; exact bound-based pruning and N-2 verification remain governed by the underlying branch-and-bound procedure. A feasibility-preservation result shows that any reported solution satisfies the prescribed N-2 capacity-support condition. Case study results show that the proposed method reduces the power deficit to zero under typical N-2 contingencies by establishing a medium-voltage DC through-feeding section and flexible interconnection channels. Compared with the reference case, the main configuration cost increases by 12.5%, indicating that the proposed method can enhance the system’s support capability under severe contingencies at the expense of a moderate increase in configuration cost.

Applied System InnovationVol. 9(9)
National Institute of Clean and Low-Carbon Energy (CN)
Affordable and clean energy
Openalex Percentile: Top 10%
Railway Systems and Energy Efficiency
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.