A constraint programming-based decomposition procedure for shop scheduling problems

In this paper, we propose a two-phase constraint programming (CP) based algorithm to obtain high-quality lower and upper bounds for classical scheduling problems under the makespan minimisation criterion. The method relies on a resource-constrained project scheduling problem (RCPSP) formulation that incorporates a decomposition approach and a warm-start mechanism exploiting the problem structure to derive competitive bounds. We evaluate our approach on 280 instances of the non-permutation flow shop scheduling problem (NPFSSP) and the job shop scheduling problem (JSSP), comprising 120 and 160 instances, respectively. A comprehensive computational analysis shows that the proposed decomposition approach (DA) is highly competitive in terms of optimality gap and relative percentage deviation with respect to both the lower and upper bounds, outperforming a direct solution (DS) approach commonly used in industrial practice. DA consistently dominates DS across most instance subsets, both in average performance and in variability. We further validate our approach on 20 real-world industrial instances featuring non-rectangular job structures, job recirculation, and unbalanced machine workloads, reaching the optimal makespan on all instances in an average of 251 s. By obtaining highly competitive bounds, our proposed decomposition procedure increases managerial confidence when committing to due dates, allocating workloads, or evaluating whether additional capacity is required.

Authors

Institutions

Publication Details

Journal
International Journal of Production Research
Published
2026-08-24
DOI
https://doi.org/10.1080/00207543.2026.2719849
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A constraint programming-based decomposition procedure for shop scheduling problems

Armin Lüer‐Villagra, Daniel Alejandro Rossit, Francisco Yuraszeck, Gonzalo Mejía
International Journal of Production Research
Resource-Constrained Project Scheduling
article

A constraint programming-based decomposition procedure for shop scheduling problems

Armin Lüer‐Villagra, Daniel Alejandro Rossit, Francisco Yuraszeck, Gonzalo Mejía
article en

Abstract

In this paper, we propose a two-phase constraint programming (CP) based algorithm to obtain high-quality lower and upper bounds for classical scheduling problems under the makespan minimisation criterion. The method relies on a resource-constrained project scheduling problem (RCPSP) formulation that incorporates a decomposition approach and a warm-start mechanism exploiting the problem structure to derive competitive bounds. We evaluate our approach on 280 instances of the non-permutation flow shop scheduling problem (NPFSSP) and the job shop scheduling problem (JSSP), comprising 120 and 160 instances, respectively. A comprehensive computational analysis shows that the proposed decomposition approach (DA) is highly competitive in terms of optimality gap and relative percentage deviation with respect to both the lower and upper bounds, outperforming a direct solution (DS) approach commonly used in industrial practice. DA consistently dominates DS across most instance subsets, both in average performance and in variability. We further validate our approach on 20 real-world industrial instances featuring non-rectangular job structures, job recirculation, and unbalanced machine workloads, reaching the optimal makespan on all instances in an average of 251 s. By obtaining highly competitive bounds, our proposed decomposition procedure increases managerial confidence when committing to due dates, allocating workloads, or evaluating whether additional capacity is required.

International Journal of Production Research
Universidad Andrés Bello (CL), Consejo Nacional de Investigaciones Científicas y Técnicas (AR), Universidad de La Sabana (CO), Universidad Nacional del Sur (AR)
Decent work and economic growth
Openalex Percentile: Top 6%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A constraint programming-based decomposition procedure for shop scheduling problems — Armin Lüer‐Villagra, Daniel Alejandro Rossit, et al. · International Journal of Production Research (2026) | TGRS Research Map | TGRS