Integrated construction scheme and critical path search for scheduling with reentrant and skippable operations in real-world hybrid flowshop

This paper investigates a complex scheduling problem originating from real-world pharmaceutical workshops, characterised by the coexistence of reentrant and skippable operations, which we define as the hybrid flowshop scheduling problem with reentrant and skippable operations (HFSP_RAS). The core challenge lies in effectively handling cross-stage operational dependencies, along with strict machine cleaning and transfer time constraints. To accurately capture these complex industrial constraints and to provide highly effective exact benchmarks, two mathematical models are developed: a Mixed-Integer Linear Programming (MILP) model and a Constraint Programming (CP) model. Considering the demand for real-time computational efficiency in modern manufacturing, we further develop a heuristic approach that integrates a Construction Scheme (CS) and Critical Path Search (CPS), named CS-CPS. Specifically, the CS adopts a dual-job encoding and a two-phase active decoding mechanism to generate high-quality initial schedules. The CPS further improves the solutions by introducing a critical-path-based search and a neighbourhood pruning strategy. This paper compares the CS-CPS with the MILP and CP models, constructive heuristics, and metaheuristics. The results demonstrate that the proposed CS-CPS, while bridging the computational gap of exact solvers, consistently outperforms the compared algorithms in terms of solution quality and stability. Finally, validation based on real-world production data further confirms its superiority.

Authors

Institutions

Publication Details

Journal
International Journal of Production Research
Published
2026-07-30
DOI
https://doi.org/10.1080/00207543.2026.2708152
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrated construction scheme and critical path search for scheduling with reentrant and skippable operations in real-world hybrid flowshop

Xuchu Jiang, Biao Zhang, Leilei Meng, X.S. Zhang et al.
International Journal of Production Research
Resource-Constrained Project Scheduling
article

Integrated construction scheme and critical path search for scheduling with reentrant and skippable operations in real-world hybrid flowshop

Xuchu Jiang, Biao Zhang, Leilei Meng, X.S. Zhang, Hongyan Sang
article en

Abstract

This paper investigates a complex scheduling problem originating from real-world pharmaceutical workshops, characterised by the coexistence of reentrant and skippable operations, which we define as the hybrid flowshop scheduling problem with reentrant and skippable operations (HFSP_RAS). The core challenge lies in effectively handling cross-stage operational dependencies, along with strict machine cleaning and transfer time constraints. To accurately capture these complex industrial constraints and to provide highly effective exact benchmarks, two mathematical models are developed: a Mixed-Integer Linear Programming (MILP) model and a Constraint Programming (CP) model. Considering the demand for real-time computational efficiency in modern manufacturing, we further develop a heuristic approach that integrates a Construction Scheme (CS) and Critical Path Search (CPS), named CS-CPS. Specifically, the CS adopts a dual-job encoding and a two-phase active decoding mechanism to generate high-quality initial schedules. The CPS further improves the solutions by introducing a critical-path-based search and a neighbourhood pruning strategy. This paper compares the CS-CPS with the MILP and CP models, constructive heuristics, and metaheuristics. The results demonstrate that the proposed CS-CPS, while bridging the computational gap of exact solvers, consistently outperforms the compared algorithms in terms of solution quality and stability. Finally, validation based on real-world production data further confirms its superiority.

International Journal of Production Research
Zhongnan University of Economics and Law (CN), Liaocheng University (CN)
National Natural Science Foundation of China, Natural Science Foundation of Shandong Province
Industry, innovation and infrastructure
Openalex Percentile: Top 6%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.