Constraint-based analysis of civil work delays in utility-scale solar farm construction: a multiple-case study in Thailand

Purpose - This study examines how different types of constraints influence delay outcomes in utility-scale solar farm civil construction and proposes a constraint-based taxonomy comprising Physical, Socio-environmental and Technical-operational categories. It also introduces Earthwork Volume Intensity (EVI, m³/MWp) as a terrain-normalised indicator of earthwork demand. Design/methodology/approach - A multiple-case study design is applied to eight solar farm projects in Thailand (169 MWp total) delivered under standardised equipment and contractual conditions. Primary schedule data are analysed through cross-case pattern analysis and exploratory statistical methods, including Pearson correlation, ordinary least squares regression and the MannWhitney U test. Findings - Within hillside terrain, EVI provides a more consistent explanation of delay severity than project scale, indicating a direct link between terrain-driven workload and schedule performance. Hillside projects experienced substantially higher earthwork delays (36- 57%) than flat-terrain projects, while foundation delays were effectively mitigated through a change in construction method (driven concrete to steel screw piles). The apparent correlation between project scale and delay reflects outlier leverage rather than a causal mechanism. Research limitations/implications - The sample size (n = 8) and single-organisation data source limit statistical power and generalisability. EVI is positioned as a planning-oriented diagnostic rather than a statistically validated predictor; validation across larger, multi-organisation datasets is required. Practical implications - The constraint taxonomy and EVI metric provide a structured pre-construction decision framework supporting differentiated contingency allocation by terrain type, agricultural-calendar coordination for socio-environmental risks and geotechnical-informed foundation selection. Owner’s Engineers managing multi-site portfolios can apply the framework using routinely collected schedule data. Originality/value - This is the first study to apply a constraint-based delay taxonomy to solar farm civil construction and to introduce EVI as a terrainderived schedule risk indicator. The single-organisation controlled design isolates terrain effects from confounders typically present in multi-organisation construction delay studies.

Authors

Institutions

Publication Details

Journal
Journal of Asian Architecture and Building Engineering
Published
2026-08-26
DOI
https://doi.org/10.1080/13467581.2026.2721941
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Constraint-based analysis of civil work delays in utility-scale solar farm construction: a multiple-case study in Thailand

Kongpop Watcharasawe, Nonpawit Chuntarapadit
Journal of Asian Architecture and Building Engineering
Construction Project Management and Performance
article

Constraint-based analysis of civil work delays in utility-scale solar farm construction: a multiple-case study in Thailand

Kongpop Watcharasawe, Nonpawit Chuntarapadit
article en

Abstract

Purpose - This study examines how different types of constraints influence delay outcomes in utility-scale solar farm civil construction and proposes a constraint-based taxonomy comprising Physical, Socio-environmental and Technical-operational categories. It also introduces Earthwork Volume Intensity (EVI, m³/MWp) as a terrain-normalised indicator of earthwork demand. Design/methodology/approach - A multiple-case study design is applied to eight solar farm projects in Thailand (169 MWp total) delivered under standardised equipment and contractual conditions. Primary schedule data are analysed through cross-case pattern analysis and exploratory statistical methods, including Pearson correlation, ordinary least squares regression and the MannWhitney U test. Findings - Within hillside terrain, EVI provides a more consistent explanation of delay severity than project scale, indicating a direct link between terrain-driven workload and schedule performance. Hillside projects experienced substantially higher earthwork delays (36- 57%) than flat-terrain projects, while foundation delays were effectively mitigated through a change in construction method (driven concrete to steel screw piles). The apparent correlation between project scale and delay reflects outlier leverage rather than a causal mechanism. Research limitations/implications - The sample size (n = 8) and single-organisation data source limit statistical power and generalisability. EVI is positioned as a planning-oriented diagnostic rather than a statistically validated predictor; validation across larger, multi-organisation datasets is required. Practical implications - The constraint taxonomy and EVI metric provide a structured pre-construction decision framework supporting differentiated contingency allocation by terrain type, agricultural-calendar coordination for socio-environmental risks and geotechnical-informed foundation selection. Owner’s Engineers managing multi-site portfolios can apply the framework using routinely collected schedule data. Originality/value - This is the first study to apply a constraint-based delay taxonomy to solar farm civil construction and to introduce EVI as a terrainderived schedule risk indicator. The single-organisation controlled design isolates terrain effects from confounders typically present in multi-organisation construction delay studies.

Journal of Asian Architecture and Building Engineering
Rajamangala University of Technology Rattanakosin (TH), Institute of Power Engineering (PL)
Openalex Percentile: Top 18%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.