Automated conceptual earned value management

Traditional Earned Value Management (EVM) is one of the most widely adopted project-control methodologies; however, its application is fundamentally constrained during the conceptual stage because reliable cost, schedule, variance, and risk assessments cannot be generated before actual project progress data becomes available. This paper introduces Automated Conceptual Earned Value Management (ACEVM), a novel project-control concept, methodology, and decision-support framework that extends EVM from a retrospective performance-monitoring tool into a predictive, proactive and intelligent project-control system. ACEVM enables the automated estimation of Budget at Completion, Duration at Completion, Cost Variance, Schedule Variance, and Conceptual Project Risk using limited early-stage project information before project execution begins. The framework was developed and validated using 1,277 completed Field Canal Improvement Projects (FCIPs). Twenty-five predictors were screened through factor analysis and stepwise regression and used to train 60 optimized machine-learning model instances, defined as 12 candidate algorithms evaluated across five ACEVM prediction outputs. Hyperparameters were optimized using the Artificial Bee Colony algorithm, while model evaluation considered predictive accuracy, robustness, explainability, and computational CO 2 emissions. The best-performing models were LightGBM for budget prediction, Extremely Randomized Trees for duration and cost variance prediction, AdaBoost for duration variance prediction, and Extremely Randomized Trees for risk classification.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2026-07-25
DOI
https://doi.org/10.1038/s41598-026-61909-5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Automated conceptual earned value management

Abdulaziz Alotaibi, Haytham H. Elmousalami
Scientific Reports
Construction Project Management and Performance
article

Automated conceptual earned value management

Abdulaziz Alotaibi, Haytham H. Elmousalami
article en

Abstract

Traditional Earned Value Management (EVM) is one of the most widely adopted project-control methodologies; however, its application is fundamentally constrained during the conceptual stage because reliable cost, schedule, variance, and risk assessments cannot be generated before actual project progress data becomes available. This paper introduces Automated Conceptual Earned Value Management (ACEVM), a novel project-control concept, methodology, and decision-support framework that extends EVM from a retrospective performance-monitoring tool into a predictive, proactive and intelligent project-control system. ACEVM enables the automated estimation of Budget at Completion, Duration at Completion, Cost Variance, Schedule Variance, and Conceptual Project Risk using limited early-stage project information before project execution begins. The framework was developed and validated using 1,277 completed Field Canal Improvement Projects (FCIPs). Twenty-five predictors were screened through factor analysis and stepwise regression and used to train 60 optimized machine-learning model instances, defined as 12 candidate algorithms evaluated across five ACEVM prediction outputs. Hyperparameters were optimized using the Artificial Bee Colony algorithm, while model evaluation considered predictive accuracy, robustness, explainability, and computational CO 2 emissions. The best-performing models were LightGBM for budget prediction, Extremely Randomized Trees for duration and cost variance prediction, AdaBoost for duration variance prediction, and Extremely Randomized Trees for risk classification.

Scientific Reports
The University of Melbourne (AU), Islamic University of Madinah (SA)
Openalex Percentile: Top 5%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.