Method for implementing scheduling systems in discrete-continuous production: the case of oil refineries

This paper addresses the complex problem of production scheduling for continuous production facilities, such as oil refineries and petrochemical plants. The typical challenges of existing models are analyzed in detail, including the difficulty of accounting for all technological and logistic constraints, operational challenges, and the limited time available for schedule preparation and verification. As a solution, a five-step implementation methodology is proposed: 1) model aggregation to ensure solvability and accuracy, 2) selection of data updating methods (manual, semi-automated, or fully automated), 3) user adaptation through a structured planning process and automatic checks, 4) ensuring additivity between monthly plans based on linear programming and shift-daily schedules, and 5) automatic monitoring of plan and actual asynchrony to detect deviations. The methodology is embedded into the system implementation process, linking methodological principles with each project stage. It constitutes a replicable approach applicable to petrochemical and other continuous production facilities, ensuring the creation of a robust and adequate system capable of operating under the high dynamics and complexity of modern production.

Authors

Institutions

Publication Details

Journal
St. Petersburg State Polytechnical University Journal
Published
2026-07-24
DOI
https://doi.org/10.18721/jcstcs.19208
Primary Topic
Process Optimization and Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Method for implementing scheduling systems in discrete-continuous production: the case of oil refineries

Renat Shaidullin
St. Petersburg State Polytechnical University Journal
Process Optimization and Integration
article

Method for implementing scheduling systems in discrete-continuous production: the case of oil refineries

Renat Shaidullin
article en

Abstract

This paper addresses the complex problem of production scheduling for continuous production facilities, such as oil refineries and petrochemical plants. The typical challenges of existing models are analyzed in detail, including the difficulty of accounting for all technological and logistic constraints, operational challenges, and the limited time available for schedule preparation and verification. As a solution, a five-step implementation methodology is proposed: 1) model aggregation to ensure solvability and accuracy, 2) selection of data updating methods (manual, semi-automated, or fully automated), 3) user adaptation through a structured planning process and automatic checks, 4) ensuring additivity between monthly plans based on linear programming and shift-daily schedules, and 5) automatic monitoring of plan and actual asynchrony to detect deviations. The methodology is embedded into the system implementation process, linking methodological principles with each project stage. It constitutes a replicable approach applicable to petrochemical and other continuous production facilities, ensuring the creation of a robust and adequate system capable of operating under the high dynamics and complexity of modern production.

St. Petersburg State Polytechnical University Journal
Peter the Great St. Petersburg Polytechnic University (RU)
Industry, innovation and infrastructure
Openalex Percentile: Top 10%
Process Optimization and Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.