Escalation instability in probability-impact matrices: evidence from capital projects

Purpose Probability-impact matrices are widely embedded in project governance systems and used to prioritise risks, allocate mitigation resources and trigger management escalation. This study examines whether commonly used qualitative risk matrices preserve relative risk prioritisation when compared to quantitative assessments of the same risks. Design/methodology/approach The study analyses 1,144 paired qualitative and quantitative risk assessments from 91 mining capital projects across 43 organisations. Paired nonparametric tests, distributional comparisons, Wasserstein distance metrics and colour-band reclassification analysis are used to evaluate differences in probability ratings, impact ratings and composite risk scores. Findings Qualitative and quantitative probability ratings align at the ordinal level. In contrast, qualitative impact ratings and composite risk scores are systematically higher than their quantitative counterparts. Quantitative reassessment altered escalation colour bands in 73.3% of risks, with 59.4% moving to lower bands and 37.2% shifting by two or more categories, indicating material changes in prioritisation. These findings suggest that qualitative matrices do not reliably preserve escalation stability under alternative elicitation formats. Practical implications When escalation outcomes depend on representational format, risk-informed governance becomes structurally unstable. Hybrid configurations that separate qualitative communication from quantitative decision support can enhance decision quality and improve the robustness of prioritisation and contingency allocation. Originality/value The study introduces escalation stability as a practical criterion for evaluating risk assessment tools and provides large-sample empirical evidence that elicitation format materially influences risk prioritisation in capital projects.

Authors

Institutions

Publication Details

Journal
International Journal of Managing Projects in Business
Published
2026-07-16
DOI
https://doi.org/10.1108/ijmpb-02-2026-0086
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Escalation instability in probability-impact matrices: evidence from capital projects

Werner G. Meyer
International Journal of Managing Projects in Business
Construction Project Management and Performance
article

Escalation instability in probability-impact matrices: evidence from capital projects

Werner G. Meyer
article en

Abstract

Purpose Probability-impact matrices are widely embedded in project governance systems and used to prioritise risks, allocate mitigation resources and trigger management escalation. This study examines whether commonly used qualitative risk matrices preserve relative risk prioritisation when compared to quantitative assessments of the same risks. Design/methodology/approach The study analyses 1,144 paired qualitative and quantitative risk assessments from 91 mining capital projects across 43 organisations. Paired nonparametric tests, distributional comparisons, Wasserstein distance metrics and colour-band reclassification analysis are used to evaluate differences in probability ratings, impact ratings and composite risk scores. Findings Qualitative and quantitative probability ratings align at the ordinal level. In contrast, qualitative impact ratings and composite risk scores are systematically higher than their quantitative counterparts. Quantitative reassessment altered escalation colour bands in 73.3% of risks, with 59.4% moving to lower bands and 37.2% shifting by two or more categories, indicating material changes in prioritisation. These findings suggest that qualitative matrices do not reliably preserve escalation stability under alternative elicitation formats. Practical implications When escalation outcomes depend on representational format, risk-informed governance becomes structurally unstable. Hybrid configurations that separate qualitative communication from quantitative decision support can enhance decision quality and improve the robustness of prioritisation and contingency allocation. Originality/value The study introduces escalation stability as a practical criterion for evaluating risk assessment tools and provides large-sample empirical evidence that elicitation format materially influences risk prioritisation in capital projects.

International Journal of Managing Projects in BusinessVol. 19(8)
University of Pretoria (ZA)
Openalex Percentile: Top 5%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.