An Integrated Decision Support Model for Early Planning in Off-Site Construction Projects

The construction industry is evolving toward more standardized, supply chain-oriented, modular, and integrated practices. This research introduces a novel transition matrix-based mixed-integer linear programming (MILP) model that optimizes modular construction (MC) design alongside supply chain decisions. The model incorporates real-world factors, such as modular element selection, supplier identification, and process sequencing and timing. Its unique contribution lies in the simultaneous optimization of both design and supply chain decisions within a unified framework. The model also enables sensitivity analysis on design choices, supplier alternatives, and productivity, supporting robust scenario planning and risk mitigation. Applied to both small and large-scale instances, the model proves computationally efficient and practical for real-world use. Results show that higher upfront investments in MC lead to improved inventory control, lower onsite costs, significantly shorter project durations, up to 44% faster completion, and 86% reduction in onsite work. The model fills existing research gaps by integrating decisions of MC, supply chain, and project management, offering a valuable project planning tool for general contractors. The model enhances early-phase decision making, collaboration, and cost-effectiveness while providing detailed insights into supplier management and the performance impact of modularity.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2026-06-28
DOI
https://doi.org/10.1061/jcemd4.coeng-18111
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An Integrated Decision Support Model for Early Planning in Off-Site Construction Projects

Amin Chaabane, Sharfuddin Ahmed Khan, Muhammad Atiq Ur Rehman
Journal of Construction Engineering and Management
BIM and Construction Integration
article

An Integrated Decision Support Model for Early Planning in Off-Site Construction Projects

Amin Chaabane, Sharfuddin Ahmed Khan, Muhammad Atiq Ur Rehman
article en

Abstract

The construction industry is evolving toward more standardized, supply chain-oriented, modular, and integrated practices. This research introduces a novel transition matrix-based mixed-integer linear programming (MILP) model that optimizes modular construction (MC) design alongside supply chain decisions. The model incorporates real-world factors, such as modular element selection, supplier identification, and process sequencing and timing. Its unique contribution lies in the simultaneous optimization of both design and supply chain decisions within a unified framework. The model also enables sensitivity analysis on design choices, supplier alternatives, and productivity, supporting robust scenario planning and risk mitigation. Applied to both small and large-scale instances, the model proves computationally efficient and practical for real-world use. Results show that higher upfront investments in MC lead to improved inventory control, lower onsite costs, significantly shorter project durations, up to 44% faster completion, and 86% reduction in onsite work. The model fills existing research gaps by integrating decisions of MC, supply chain, and project management, offering a valuable project planning tool for general contractors. The model enhances early-phase decision making, collaboration, and cost-effectiveness while providing detailed insights into supplier management and the performance impact of modularity.

Journal of Construction Engineering and ManagementVol. 152(9)
University of Regina (CA), École de Technologie Supérieure (CA)
Industry, innovation and infrastructure
Openalex Percentile: Top 10%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.