Field Performance of a Pile-Cap Ground Improvement System for High-Speed Railway Embankments in Karst Terrain

High-speed railway embankments constructed over karst-prone ground conditions are often challenged by weak soils and subsurface cavities, which can lead to instability and excessive settlement. This study presents a full-scale field investigation conducted in the El-Gharbaniyat area, west of Alexandria, Egypt, where a pile–cap ground improvement system was implemented to support a high-speed railway embankment founded on clayey and silty soils overlying fractured limestone. A comprehensive site investigation program was performed, including 28 boreholes and integrated geophysical surveys using Electrical Resistivity Tomography (ERT) and Seismic Tomography (ST), enabling improved identification of weak zones and cavity-prone formations. Based on these findings, a pile–cap system was designed using reinforced concrete piles of 0.60 m diameter and an average length of 29 m, arranged in a 4 × 4 m grid and capped with reinforced concrete footings to ensure efficient load transfer to deeper competent strata. The system performance was validated through laboratory testing and full-scale in situ pile load tests. The average 28-day compressive strength of 122 tested piles reached approximately 50 MPa, exceeding the design value by approximately 30%. Load test results showed settlements ranging from 1.08 to 2.76 mm at the working load (2200 kN) and 2.16 to 5.10 mm at the maximum load (3300 kN), all well below allowable limits. Comparative evaluation indicated that the proposed system achieves significant material savings (>90%), lower treatment cost (150 USD/m2), reduced carbon emission (5.7 t per pile), and shorter construction duration (7 h per pile). These findings confirm that the pile–cap system provides a robust, cost-effective, and environmentally efficient solution for ground improvement in karst environments.

Authors

Institutions

Publication Details

Journal
Infrastructures
Published
2026-06-25
DOI
https://doi.org/10.3390/infrastructures11070217
Primary Topic
Karst Systems and Hydrogeology
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Field Performance of a Pile-Cap Ground Improvement System for High-Speed Railway Embankments in Karst Terrain

Mahmoud Abo El-Wafa, Ahmed S. Eisa, Yehia Miky, Mohamed A. Badran et al.
Infrastructures
Karst Systems and Hydrogeology
article

Field Performance of a Pile-Cap Ground Improvement System for High-Speed Railway Embankments in Karst Terrain

Mahmoud Abo El-Wafa, Ahmed S. Eisa, Yehia Miky, Mohamed A. Badran, Hilal Hassan
article en

Abstract

High-speed railway embankments constructed over karst-prone ground conditions are often challenged by weak soils and subsurface cavities, which can lead to instability and excessive settlement. This study presents a full-scale field investigation conducted in the El-Gharbaniyat area, west of Alexandria, Egypt, where a pile–cap ground improvement system was implemented to support a high-speed railway embankment founded on clayey and silty soils overlying fractured limestone. A comprehensive site investigation program was performed, including 28 boreholes and integrated geophysical surveys using Electrical Resistivity Tomography (ERT) and Seismic Tomography (ST), enabling improved identification of weak zones and cavity-prone formations. Based on these findings, a pile–cap system was designed using reinforced concrete piles of 0.60 m diameter and an average length of 29 m, arranged in a 4 × 4 m grid and capped with reinforced concrete footings to ensure efficient load transfer to deeper competent strata. The system performance was validated through laboratory testing and full-scale in situ pile load tests. The average 28-day compressive strength of 122 tested piles reached approximately 50 MPa, exceeding the design value by approximately 30%. Load test results showed settlements ranging from 1.08 to 2.76 mm at the working load (2200 kN) and 2.16 to 5.10 mm at the maximum load (3300 kN), all well below allowable limits. Comparative evaluation indicated that the proposed system achieves significant material savings (>90%), lower treatment cost (150 USD/m2), reduced carbon emission (5.7 t per pile), and shorter construction duration (7 h per pile). These findings confirm that the pile–cap system provides a robust, cost-effective, and environmentally efficient solution for ground improvement in karst environments.

InfrastructuresVol. 11(7)
King Abdulaziz University (SA), Zagazig University (EG), Land Transport Authority (SG)
Life in Land
Openalex Percentile: Top 8%
Karst Systems and Hydrogeology
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.