Systemic Productivity Constraints in Decentralised Public Building Delivery: Evidence from District-level Projects in Uganda

<ns5:p>Background This study evaluates systemic productivity constraints within decentralized public building projects in Uganda, where infrastructure delivery often faces significant delays and cost overruns. The research aims to identifies, ranks, and evaluates these constraints while assessing the level of consensus among different construction professional groups regarding the primary drivers of productivity loss. Method A mixed-methods research design was employed, integrating quantitative data from a survey of 105 construction professionals (including engineers, architects, and project managers) with qualitative insights from site observations and key-informant interviews. Data analysis utilized the Relative Importance Index (RII) to rank 32 identified productivity factors and Spearman’s rank correlation to determine the degree of inter-professional agreement on these rankings. Results The findings reveal that “Delay in payments” (RII = 0.857) is the most critical constraint affecting productivity, followed by “Inadequate site management and supervision” (RII = 0.841) and “Lack of competent staff” (RII = 0.834). High Spearman’s correlation coefficients (ranging from 0.818 to 0.891) indicate a strong consensus across professional groups, suggesting that productivity bottlenecks are systemic and institutional rather than isolated to specific technical disciplines. Conclusion The study concludes that productivity in decentralized project delivery is primarily hindered by cross-cutting administrative and management deficiencies. Addressing these constraints requires streamlined payment certification processes and the strengthening of supervisory capacity at the district level. These results provide a diagnostic framework for policy makers to implement targeted institutional reforms to improve the efficiency of routine public building programs.</ns5:p>

Authors

Institutions

Publication Details

Journal
F1000Research
Published
2026-06-18
DOI
https://doi.org/10.12688/f1000research.180617.1
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Systemic Productivity Constraints in Decentralised Public Building Delivery: Evidence from District-level Projects in Uganda

Chikadibia Kalu Awa Uche, Kelechi John Ukagwu, Paul Yohanna, Obinna Onyebuchi Barah et al.
F1000Research
Construction Project Management and Performance
article

Systemic Productivity Constraints in Decentralised Public Building Delivery: Evidence from District-level Projects in Uganda

Chikadibia Kalu Awa Uche, Kelechi John Ukagwu, Paul Yohanna, Obinna Onyebuchi Barah, Bubu Pius Erheyovwe, Valentine Hyginus Udoka Eze
article en

Abstract

<ns5:p>Background This study evaluates systemic productivity constraints within decentralized public building projects in Uganda, where infrastructure delivery often faces significant delays and cost overruns. The research aims to identifies, ranks, and evaluates these constraints while assessing the level of consensus among different construction professional groups regarding the primary drivers of productivity loss. Method A mixed-methods research design was employed, integrating quantitative data from a survey of 105 construction professionals (including engineers, architects, and project managers) with qualitative insights from site observations and key-informant interviews. Data analysis utilized the Relative Importance Index (RII) to rank 32 identified productivity factors and Spearman’s rank correlation to determine the degree of inter-professional agreement on these rankings. Results The findings reveal that “Delay in payments” (RII = 0.857) is the most critical constraint affecting productivity, followed by “Inadequate site management and supervision” (RII = 0.841) and “Lack of competent staff” (RII = 0.834). High Spearman’s correlation coefficients (ranging from 0.818 to 0.891) indicate a strong consensus across professional groups, suggesting that productivity bottlenecks are systemic and institutional rather than isolated to specific technical disciplines. Conclusion The study concludes that productivity in decentralized project delivery is primarily hindered by cross-cutting administrative and management deficiencies. Addressing these constraints requires streamlined payment certification processes and the strengthening of supervisory capacity at the district level. These results provide a diagnostic framework for policy makers to implement targeted institutional reforms to improve the efficiency of routine public building programs.</ns5:p>

F1000ResearchVol. 15
Mbarara University of Science and Technology (UG), Kampala International University (UG)
Industry, innovation and infrastructure
Openalex Percentile: Top 4%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.