Predicting manpower allocation for landscape construction projects using XGBoost and SHAP

Purpose This study focuses on predicting manpower allocation for landscape construction projects using the eXtreme Gradient Boosting (XGBoost) algorithm combined with SHapley Additive Explanations (SHAP) to enhance workforce planning in response to growing labor shortages in Taiwan's construction industry. Design/methodology/approach Based on the convenient sampling concept, a dataset of 1,557 records was collected from public landscape projects executed in the North Taiwan, featuring major variables including project count, type, and calendar month. To enhance workforce planning in response to growing labor shortages in Taiwan's construction industry, the framework employs an interpretable labor forecasting model based on the proposed methods to improve workforce deployment efficiency and reduce the risks and cost overruns associated with labor shortages. Findings The results yielded by XGBoost and SHAP show that the proposed model achieved a high predictive accuracy (R2 = 0.892), and that labor demand is most influenced by project density, task type and seasonal variation. SHAP analysis further confirmed that the model provides interpretable insights into workforce trends. This forecasting framework offers practical value by enabling (1) early identification of peak labor periods for scheduling and outsourcing and (2) improves labor allocation with project demand in urban landscape planning. Originality/value These findings highlight the task-intensive and time-sensitive nature of landscape construction, where workforce scheduling often reflects project density as a core operational logic. Overall, the findings contribute to data-informed decision-making in construction workforce management.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2026-06-09
DOI
https://doi.org/10.1108/ecam-11-2025-1919
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Predicting manpower allocation for landscape construction projects using XGBoost and SHAP

Tzuyang Yu, J C Chen, Lian Shen
Engineering Construction & Architectural Management
Construction Project Management and Performance
article

Predicting manpower allocation for landscape construction projects using XGBoost and SHAP

Tzuyang Yu, J C Chen, Lian Shen
article en

Abstract

Purpose This study focuses on predicting manpower allocation for landscape construction projects using the eXtreme Gradient Boosting (XGBoost) algorithm combined with SHapley Additive Explanations (SHAP) to enhance workforce planning in response to growing labor shortages in Taiwan's construction industry. Design/methodology/approach Based on the convenient sampling concept, a dataset of 1,557 records was collected from public landscape projects executed in the North Taiwan, featuring major variables including project count, type, and calendar month. To enhance workforce planning in response to growing labor shortages in Taiwan's construction industry, the framework employs an interpretable labor forecasting model based on the proposed methods to improve workforce deployment efficiency and reduce the risks and cost overruns associated with labor shortages. Findings The results yielded by XGBoost and SHAP show that the proposed model achieved a high predictive accuracy (R2 = 0.892), and that labor demand is most influenced by project density, task type and seasonal variation. SHAP analysis further confirmed that the model provides interpretable insights into workforce trends. This forecasting framework offers practical value by enabling (1) early identification of peak labor periods for scheduling and outsourcing and (2) improves labor allocation with project demand in urban landscape planning. Originality/value These findings highlight the task-intensive and time-sensitive nature of landscape construction, where workforce scheduling often reflects project density as a core operational logic. Overall, the findings contribute to data-informed decision-making in construction workforce management.

Engineering Construction & Architectural Management
National Central University (TW), University of Massachusetts Boston (US)
Openalex Percentile: Top 5%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Predicting manpower allocation for landscape construction projects using XGBoost and SHAP — Tzuyang Yu, J C Chen, et al. · Engineering Construction & Architectural Management (2026) | TGRS Research Map | TGRS