A coupled task scheduling approximation algorithm for minimizing the sum of completion times

Abstract In the considered coupled task problem (CTP) we have to schedule n jobs on a single machine, each consisting of two tasks with exact time delay between them, while the objective is to minimize the total completion time of the jobs. We analyze a greedy type algorithm – called SDF (Shortest Delay First) – from worst case point of view, and we give bounds for the asymptotic behavior of SDF for the special case where each task has equal length processing time p . For this case, the best-known upper bound on the asymptotic performance ratio of algorithm SDF is $$\frac{5}{3}\approx 1.666\ldots .$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mrow> <mml:mfrac> <mml:mn>5</mml:mn> <mml:mn>3</mml:mn> </mml:mfrac> <mml:mo>≈</mml:mo> <mml:mn>1.666</mml:mn> <mml:mo>…</mml:mo> <mml:mo>.</mml:mo> </mml:mrow> </mml:math> We improve this bound to a general upper bound $$\frac{21p-\sqrt{3(43p^2-28p+4)}-6}{6p}$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mfrac> <mml:mrow> <mml:mn>21</mml:mn> <mml:mi>p</mml:mi> <mml:mo>-</mml:mo> <mml:msqrt> <mml:mrow> <mml:mn>3</mml:mn> <mml:mo>(</mml:mo> <mml:mn>43</mml:mn> <mml:msup> <mml:mi>p</mml:mi> <mml:mn>2</mml:mn> </mml:msup> <mml:mo>-</mml:mo> <mml:mn>28</mml:mn> <mml:mi>p</mml:mi> <mml:mo>+</mml:mo> <mml:mn>4</mml:mn> <mml:mo>)</mml:mo> </mml:mrow> </mml:msqrt> <mml:mo>-</mml:mo> <mml:mn>6</mml:mn> </mml:mrow> <mml:mrow> <mml:mn>6</mml:mn> <mml:mi>p</mml:mi> </mml:mrow> </mml:mfrac> </mml:math> that holds for all $$p\ge 2.$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mrow> <mml:mi>p</mml:mi> <mml:mo>≥</mml:mo> <mml:mn>2</mml:mn> <mml:mo>.</mml:mo> </mml:mrow> </mml:math> Using constructions to compute lower bounds, we give narrow intervals for the asymptotic behavior of algorithm SDF as a function of the parameter p .

Authors

Institutions

Publication Details

Journal
Annals of Operations Research
Published
2026-05-21
DOI
https://doi.org/10.1007/s10479-026-07261-3
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A coupled task scheduling approximation algorithm for minimizing the sum of completion times

József Békési, Gábor Galambos, György Dósa
Annals of Operations Research
Scheduling and Optimization Algorithms
article

A coupled task scheduling approximation algorithm for minimizing the sum of completion times

József Békési, Gábor Galambos, György Dósa
article en

Abstract

Abstract In the considered coupled task problem (CTP) we have to schedule n jobs on a single machine, each consisting of two tasks with exact time delay between them, while the objective is to minimize the total completion time of the jobs. We analyze a greedy type algorithm – called SDF (Shortest Delay First) – from worst case point of view, and we give bounds for the asymptotic behavior of SDF for the special case where each task has equal length processing time p . For this case, the best-known upper bound on the asymptotic performance ratio of algorithm SDF is $$\frac{5}{3}\approx 1.666\ldots .$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mrow> <mml:mfrac> <mml:mn>5</mml:mn> <mml:mn>3</mml:mn> </mml:mfrac> <mml:mo>≈</mml:mo> <mml:mn>1.666</mml:mn> <mml:mo>…</mml:mo> <mml:mo>.</mml:mo> </mml:mrow> </mml:math> We improve this bound to a general upper bound $$\frac{21p-\sqrt{3(43p^2-28p+4)}-6}{6p}$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mfrac> <mml:mrow> <mml:mn>21</mml:mn> <mml:mi>p</mml:mi> <mml:mo>-</mml:mo> <mml:msqrt> <mml:mrow> <mml:mn>3</mml:mn> <mml:mo>(</mml:mo> <mml:mn>43</mml:mn> <mml:msup> <mml:mi>p</mml:mi> <mml:mn>2</mml:mn> </mml:msup> <mml:mo>-</mml:mo> <mml:mn>28</mml:mn> <mml:mi>p</mml:mi> <mml:mo>+</mml:mo> <mml:mn>4</mml:mn> <mml:mo>)</mml:mo> </mml:mrow> </mml:msqrt> <mml:mo>-</mml:mo> <mml:mn>6</mml:mn> </mml:mrow> <mml:mrow> <mml:mn>6</mml:mn> <mml:mi>p</mml:mi> </mml:mrow> </mml:mfrac> </mml:math> that holds for all $$p\ge 2.$$ <mml:math xmlns:mml="http://www.w3.org/1998/Math/MathML"> <mml:mrow> <mml:mi>p</mml:mi> <mml:mo>≥</mml:mo> <mml:mn>2</mml:mn> <mml:mo>.</mml:mo> </mml:mrow> </mml:math> Using constructions to compute lower bounds, we give narrow intervals for the asymptotic behavior of algorithm SDF as a function of the parameter p .

Annals of Operations Research
University of Pannonia (HU), University of Szeged (HU)
Szegedi Tudományegyetem
Decent work and economic growth
Openalex Percentile: Top 7%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A coupled task scheduling approximation algorithm for minimizing the sum of completion times — József Békési, Gábor Galambos, et al. · Annals of Operations Research (2026) | TGRS Research Map | TGRS