Time Estimation of Construction Projects based on Engineering Economics and Machine Learning

The aim of this study is to apply time estimation approaches developed based on metrics such as earned schedule (ES), earned duration (ED), and effective earned schedule (ES(e)) within the framework of earned value management (EVM) project control methodology and to model the data obtained from these approaches using machine learning (ML) methods. Accordingly, a comparative analysis of different ML methods in terms of time estimation accuracy has been performed. A dataset is created using 18 different estimated time at completion (EAC(t)) time estimation methods based on data obtained from a residential construction project in Türkiye. Using this dataset, estimation models were developed through ML techniques. The performance of six ML models employing 18-time estimation approaches was evaluated using six performance criteria. The findings indicate that the GPR model achieved superior accuracy compared to the other methods, demonstrating the strong potential of ML-based approaches for time estimation in construction projects.

Authors

Institutions

Publication Details

Journal
Canadian Journal of Civil Engineering
Published
2026-05-19
DOI
https://doi.org/10.1139/cjce-2025-0496
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time Estimation of Construction Projects based on Engineering Economics and Machine Learning

Savaş Bayram, Hatice Çıtakoğlu, Gamze Yalçın
Canadian Journal of Civil Engineering
Construction Project Management and Performance
article

Time Estimation of Construction Projects based on Engineering Economics and Machine Learning

Savaş Bayram, Hatice Çıtakoğlu, Gamze Yalçın
article en

Abstract

The aim of this study is to apply time estimation approaches developed based on metrics such as earned schedule (ES), earned duration (ED), and effective earned schedule (ES(e)) within the framework of earned value management (EVM) project control methodology and to model the data obtained from these approaches using machine learning (ML) methods. Accordingly, a comparative analysis of different ML methods in terms of time estimation accuracy has been performed. A dataset is created using 18 different estimated time at completion (EAC(t)) time estimation methods based on data obtained from a residential construction project in Türkiye. Using this dataset, estimation models were developed through ML techniques. The performance of six ML models employing 18-time estimation approaches was evaluated using six performance criteria. The findings indicate that the GPR model achieved superior accuracy compared to the other methods, demonstrating the strong potential of ML-based approaches for time estimation in construction projects.

Canadian Journal of Civil Engineering
Erciyes University (TR)
Industry, innovation and infrastructure
Openalex Percentile: Top 3%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.