Analysis of intelligent construction scheduling optimization based on reinforcement learning and its carbon emission reduction effect

Construction scheduling must balance project duration, resource allocation, and environmental sustainability under dynamic constraints. This study proposes a carbon-aware reinforcement learning–based scheduling framework using a Proximal Policy Optimization actor–critic model with task-level action masking to optimize makespan, resource feasibility, and carbon emissions simultaneously. Experimental results demonstrate that the proposed framework reduces total project duration to 600 days, achieving a 20.3% improvement over the Critical Path Method (CPM), while delivering a 43.6% reduction in total CO2 emissions compared with CPM, Genetic Algorithm, and Earliest Start methods. The framework also eliminates resource conflicts entirely, ensuring fully feasible scheduling decisions. These findings confirm that integrating carbon emission modeling directly into reinforcement learning enables adaptive, multi-objective construction scheduling that improves operational efficiency while significantly reducing environmental impact. The study establishes a practical and sustainable decision-support framework for intelligent construction planning.

Institutions

Publication Details

Journal
Discover Artificial Intelligence
Published
2026-05-19
DOI
https://doi.org/10.1007/s44163-026-01260-w
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of intelligent construction scheduling optimization based on reinforcement learning and its carbon emission reduction effect

Discover Artificial Intelligence
Resource-Constrained Project Scheduling
article

Analysis of intelligent construction scheduling optimization based on reinforcement learning and its carbon emission reduction effect

article en

Abstract

Construction scheduling must balance project duration, resource allocation, and environmental sustainability under dynamic constraints. This study proposes a carbon-aware reinforcement learning–based scheduling framework using a Proximal Policy Optimization actor–critic model with task-level action masking to optimize makespan, resource feasibility, and carbon emissions simultaneously. Experimental results demonstrate that the proposed framework reduces total project duration to 600 days, achieving a 20.3% improvement over the Critical Path Method (CPM), while delivering a 43.6% reduction in total CO2 emissions compared with CPM, Genetic Algorithm, and Earliest Start methods. The framework also eliminates resource conflicts entirely, ensuring fully feasible scheduling decisions. These findings confirm that integrating carbon emission modeling directly into reinforcement learning enables adaptive, multi-objective construction scheduling that improves operational efficiency while significantly reducing environmental impact. The study establishes a practical and sustainable decision-support framework for intelligent construction planning.

Discover Artificial Intelligence
Shanghai International Studies University (CN), Jiyang College of Zhejiang A&F University (CN), Zhejiang University of Technology (CN)
Responsible consumption and production
Openalex Percentile: Top 3%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.