Linear Programming Optimization Model for Repetitive Prefabricated Construction Projects Considering Renewable Resource Categories

Multi-building, multi-story prefabricated construction projects are notably characterized by high complexity and repetitiveness, which necessitate efficient resource scheduling. Traditional resource-constrained project scheduling problems primarily address global resources, whereas existing studies on repetitive scheduling emphasize crew allocation and often neglect constraints associated with spatially localized resources, such as tower cranes. To address the challenges posed by repetitive prefabricated construction, this study systematically analyzes scheduling characteristics and classifies renewable resources into three categories: local, crew, and global resources. This study also introduces a novel spatial precedence relationship to capture dependencies between activities on adjacent floors. A linear programming model is formulated to minimize both project duration and total resource idle time. The model is developed under several explicit simplifying assumptions to ensure computational tractability while preserving the core-resource interdependencies. The proposed model’s effectiveness is validated through an empirical case study and additional numerical experiments. In the case study, utilization rates for local resources and crews increased by 20% and 8%, respectively. Furthermore, sensitivity analysis of local-resource allocation indicates that increasing the number of tower cranes yields diminishing marginal reductions in project duration, while total resource idle time first decreases and then increases. Consequently, resource over-allocation should be avoided to prevent degradation in utilization.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-05-18
DOI
https://doi.org/10.3390/buildings16101984
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Linear Programming Optimization Model for Repetitive Prefabricated Construction Projects Considering Renewable Resource Categories

Zhentao Hu, Nanfang Cui, Wendi Tian, Dingfeng Yang
Buildings
Resource-Constrained Project Scheduling
article

Linear Programming Optimization Model for Repetitive Prefabricated Construction Projects Considering Renewable Resource Categories

Zhentao Hu, Nanfang Cui, Wendi Tian, Dingfeng Yang
article en

Abstract

Multi-building, multi-story prefabricated construction projects are notably characterized by high complexity and repetitiveness, which necessitate efficient resource scheduling. Traditional resource-constrained project scheduling problems primarily address global resources, whereas existing studies on repetitive scheduling emphasize crew allocation and often neglect constraints associated with spatially localized resources, such as tower cranes. To address the challenges posed by repetitive prefabricated construction, this study systematically analyzes scheduling characteristics and classifies renewable resources into three categories: local, crew, and global resources. This study also introduces a novel spatial precedence relationship to capture dependencies between activities on adjacent floors. A linear programming model is formulated to minimize both project duration and total resource idle time. The model is developed under several explicit simplifying assumptions to ensure computational tractability while preserving the core-resource interdependencies. The proposed model’s effectiveness is validated through an empirical case study and additional numerical experiments. In the case study, utilization rates for local resources and crews increased by 20% and 8%, respectively. Furthermore, sensitivity analysis of local-resource allocation indicates that increasing the number of tower cranes yields diminishing marginal reductions in project duration, while total resource idle time first decreases and then increases. Consequently, resource over-allocation should be avoided to prevent degradation in utilization.

BuildingsVol. 16(10)
Hubei University Of Economics (CN), Wuhan Textile University (CN), Huazhong University of Science and Technology (CN)
Hubei Provincial Department of Education, National Natural Science Foundation of China, Ministry of Education of the People's Republic of China, National Social Science Fund of China
Openalex Percentile: Top 3%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.