Monitoring and control technologies for the full-process construction of a long-span cable-stayed bridge

This study focuses on a double-tower, double-plane prestressed concrete cable-stayed bridge with a span arrangement of 75+130+365+130+75 m. A full-bridge finite element model was developed using Midas Civil, and a monitoring system was established to track main girder alignment, cable forces, and structural stresses. A phased control and monitoring strategy is implemented: alignment control is prioritized during the cantilever casting stage, while cable force and stress control take precedence during the closure stage. Monitoring results indicate that the alignment of the completed bridge's main girder is smooth, with cable force deviations controlled within 10 %, and stresses in both the main girder and pylons remaining within safe limits. This study integrates dynamic control and monitoring strategies, offering practical references for the construction control of similar bridges.

Authors

Publication Details

Journal
Vibroengineering PROCEDIA
Published
2026-04-22
DOI
https://doi.org/10.21595/vp.2026.25947
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Monitoring and control technologies for the full-process construction of a long-span cable-stayed bridge

賦 丸井, Xiaotang Wang, Zhentian Yang
Vibroengineering PROCEDIA
Structural Engineering and Vibration Analysis
article

Monitoring and control technologies for the full-process construction of a long-span cable-stayed bridge

賦 丸井, Xiaotang Wang, Zhentian Yang
article en

Abstract

This study focuses on a double-tower, double-plane prestressed concrete cable-stayed bridge with a span arrangement of 75+130+365+130+75 m. A full-bridge finite element model was developed using Midas Civil, and a monitoring system was established to track main girder alignment, cable forces, and structural stresses. A phased control and monitoring strategy is implemented: alignment control is prioritized during the cantilever casting stage, while cable force and stress control take precedence during the closure stage. Monitoring results indicate that the alignment of the completed bridge's main girder is smooth, with cable force deviations controlled within 10 %, and stresses in both the main girder and pylons remaining within safe limits. This study integrates dynamic control and monitoring strategies, offering practical references for the construction control of similar bridges.

Vibroengineering PROCEDIAVol. 61
Sustainable cities and communities
Openalex Percentile: Top 9%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.