Risk analysis of the causes of time and cost overruns in the Lebanese precast industry

Introduction The purpose of this article is to analyse the causes and risk behind time and cost overruns in the Lebanese precast sector, mainly hollow core slabs, precast beams and column. Methods The methodology includes the following steps: (i) a review of the time and cost overrun causes in the global construction industry; (ii) the use of questionnaires to identify causes specific to the Lebanese precast industry; (iii) an examination of the significance, frequency, and impact of the causes; (iv) the ranking of the causes; and (v) the performance of quantitative risk analysis. Discussion The most significant time overrun cause, according to research, is “Lack or delay of delivery of materials in markets”, while the most significant cost overrun cause is “Fluctuations in the cost of building materials”. The ranking results reveal a clear pattern: “financial management, contractual stability, and early design coordination” are the dominant determinants of both time and cost overruns in the Lebanese precast industry. According to the risk analysis study results, a project with a 50% risk level has a 37% time overrun potential and a 29% cost overrun potential. These findings imply that targeted interventions addressing the highest-probability causes can substantially reduce schedule risk, whereas cost control requires systemic and integrated strategies spanning design management, financial planning, contractual clarity, and market risk allocation. Conclusions The primary causes of time and expense overruns in the Lebanese precast sector can be identified, ranked, and evaluated for risk by owners, project managers, and engineers thanks to this study. This study is the first to examine the causes that contribute to time and cost overruns in the precast concrete sector in Lebanon.

Authors

Institutions

Publication Details

Journal
Frontiers in Built Environment
Published
2026-04-22
DOI
https://doi.org/10.3389/fbuil.2026.1763749
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk analysis of the causes of time and cost overruns in the Lebanese precast industry

Nabil Semaan, Samer El Zahab, Robert Nini
Frontiers in Built Environment
Construction Project Management and Performance
article

Risk analysis of the causes of time and cost overruns in the Lebanese precast industry

Nabil Semaan, Samer El Zahab, Robert Nini
article en

Abstract

Introduction The purpose of this article is to analyse the causes and risk behind time and cost overruns in the Lebanese precast sector, mainly hollow core slabs, precast beams and column. Methods The methodology includes the following steps: (i) a review of the time and cost overrun causes in the global construction industry; (ii) the use of questionnaires to identify causes specific to the Lebanese precast industry; (iii) an examination of the significance, frequency, and impact of the causes; (iv) the ranking of the causes; and (v) the performance of quantitative risk analysis. Discussion The most significant time overrun cause, according to research, is “Lack or delay of delivery of materials in markets”, while the most significant cost overrun cause is “Fluctuations in the cost of building materials”. The ranking results reveal a clear pattern: “financial management, contractual stability, and early design coordination” are the dominant determinants of both time and cost overruns in the Lebanese precast industry. According to the risk analysis study results, a project with a 50% risk level has a 37% time overrun potential and a 29% cost overrun potential. These findings imply that targeted interventions addressing the highest-probability causes can substantially reduce schedule risk, whereas cost control requires systemic and integrated strategies spanning design management, financial planning, contractual clarity, and market risk allocation. Conclusions The primary causes of time and expense overruns in the Lebanese precast sector can be identified, ranked, and evaluated for risk by owners, project managers, and engineers thanks to this study. This study is the first to examine the causes that contribute to time and cost overruns in the precast concrete sector in Lebanon.

Frontiers in Built EnvironmentVol. 12
University of Balamand (LB), American University of the Middle East (KW)
Industry, innovation and infrastructure
Openalex Percentile: Top 14%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.