Smart Manufacturing Scheduling Under Data Latency: A Rolling-Horizon Two-Stage MILP Framework for OEM–Tier-1 Coordination

Real-time coordination across OEM–Tier-1 manufacturing networks remains challenging due to delayed shop-floor data, stochastic machine availability, and the need for schedule stability. This paper presents a protocol-agnostic, two-stage mixed-integer linear programming (MILP) framework for real-time family-level scheduling. The method integrates MTConnect-like data streams without requiring adherence to any single communication standard. In Stage 1, a baseline plan is generated using expected capacity; in Stage 2, a rolling-horizon recourse model adapts the plan to observed (possibly lagged) capacity while incorporating a stability penalty to control resequencing. A synthetic OEM–Tier-1 testbed with three machines (two Tier-1, one OEM) is used to benchmark performance under real-time (L = 0) and delayed (L = 5) data scenarios. Across these scenarios, the real-time rolling scheduler improves strict on-time fulfillment by approximately 70% and eliminates terminal backlog relative to static planning, while MILP solve times remain under 0.1 s per cycle. Sensitivity experiments that vary disruption intensity, replanning interval (Δ), and stability weight (λ) show consistent qualitative trends and illustrate how the framework can be tuned to balance service performance against schedule stability without sacrificing computational tractability.

Authors

Institutions

Publication Details

Journal
Journal of Manufacturing and Materials Processing
Published
2026-04-21
DOI
https://doi.org/10.3390/jmmp10040142
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Smart Manufacturing Scheduling Under Data Latency: A Rolling-Horizon Two-Stage MILP Framework for OEM–Tier-1 Coordination

Shivakumar Raman, Harshkumar Kiritbhai Parmar
Journal of Manufacturing and Materials Processing
Scheduling and Optimization Algorithms
article

Smart Manufacturing Scheduling Under Data Latency: A Rolling-Horizon Two-Stage MILP Framework for OEM–Tier-1 Coordination

Shivakumar Raman, Harshkumar Kiritbhai Parmar
article en

Abstract

Real-time coordination across OEM–Tier-1 manufacturing networks remains challenging due to delayed shop-floor data, stochastic machine availability, and the need for schedule stability. This paper presents a protocol-agnostic, two-stage mixed-integer linear programming (MILP) framework for real-time family-level scheduling. The method integrates MTConnect-like data streams without requiring adherence to any single communication standard. In Stage 1, a baseline plan is generated using expected capacity; in Stage 2, a rolling-horizon recourse model adapts the plan to observed (possibly lagged) capacity while incorporating a stability penalty to control resequencing. A synthetic OEM–Tier-1 testbed with three machines (two Tier-1, one OEM) is used to benchmark performance under real-time (L = 0) and delayed (L = 5) data scenarios. Across these scenarios, the real-time rolling scheduler improves strict on-time fulfillment by approximately 70% and eliminates terminal backlog relative to static planning, while MILP solve times remain under 0.1 s per cycle. Sensitivity experiments that vary disruption intensity, replanning interval (Δ), and stability weight (λ) show consistent qualitative trends and illustrate how the framework can be tuned to balance service performance against schedule stability without sacrificing computational tractability.

Journal of Manufacturing and Materials ProcessingVol. 10(4)
University of Oklahoma (US)
Openalex Percentile: Top 17%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.