Integrated Risk Priority Assessment of Engineering and Non-Engineering Factors Influencing Saudi Arabian Construction Projects

Construction projects in Saudi Arabia face multiple risks affecting cost, schedule, and quality performance, particularly under the rapid development environment of Vision 2030. A questionnaire survey of 113 construction professionals assessed the probability and impact of engineering and non-engineering risks. Responses were analyzed using descriptive statistics and a normalized probability–impact–priority framework to derive risk priority scores (RPS) and an Overall Risk Index (ORI) across cost, time, and quality dimensions. The findings show that risk exposure is governed by both external systemic constraints and internal project governance capability. Non-engineering risks, especially inflation, statutory clearance delays, and financial transaction restrictions, exert the strongest overall influence. Engineering risks related to resource mismanagement, insufficient managerial capability, and testing and commissioning deficiencies primarily drive operational performance variability. The study proposes a normalized multidimensional risk prioritization approach that integrates cost, time, and quality impacts, providing practical guidance for improving regulatory efficiency and project management capability in Saudi construction projects.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-04-13
DOI
https://doi.org/10.3390/buildings16081518
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrated Risk Priority Assessment of Engineering and Non-Engineering Factors Influencing Saudi Arabian Construction Projects

Mohd Ahmed, Javed Mallick, D Alqahtani, Muhammad D. S. Al Shahrani
Buildings
Construction Project Management and Performance
article

Integrated Risk Priority Assessment of Engineering and Non-Engineering Factors Influencing Saudi Arabian Construction Projects

Mohd Ahmed, Javed Mallick, D Alqahtani, Muhammad D. S. Al Shahrani
article en

Abstract

Construction projects in Saudi Arabia face multiple risks affecting cost, schedule, and quality performance, particularly under the rapid development environment of Vision 2030. A questionnaire survey of 113 construction professionals assessed the probability and impact of engineering and non-engineering risks. Responses were analyzed using descriptive statistics and a normalized probability–impact–priority framework to derive risk priority scores (RPS) and an Overall Risk Index (ORI) across cost, time, and quality dimensions. The findings show that risk exposure is governed by both external systemic constraints and internal project governance capability. Non-engineering risks, especially inflation, statutory clearance delays, and financial transaction restrictions, exert the strongest overall influence. Engineering risks related to resource mismanagement, insufficient managerial capability, and testing and commissioning deficiencies primarily drive operational performance variability. The study proposes a normalized multidimensional risk prioritization approach that integrates cost, time, and quality impacts, providing practical guidance for improving regulatory efficiency and project management capability in Saudi construction projects.

BuildingsVol. 16(8)
King Khalid University (SA)
Openalex Percentile: Top 23%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.