SBT – Experiences with tunnel support using yielding elements at construction lot SBT2.1

Abstract The use of yielding elements is a highly effective method in deep rock tunnel construction for protecting the shotcrete, particularly in the early stages, from excessive stress caused by high rock loads. Installing multiple rows of yielding elements results in a ductile and flexible support. By deliberately allowing additional deformations, stresses are transferred into deeper rock regions in accordance with the NATM philosophy. Consequently, the stress‐strain relationship of the yielding elements must be adapted to the time‐dependent properties of the shotcrete in relation to the excavation rate. Experience at the SBT2.1 construction site has shown that, when using yielding elements, not only the precise location of the elements within the circumference but also their positioning within the cross‐section is key to success. It is also essential to determine the correct timing for closing the yielding elements in order to achieve a load‐bearing ring closure in a timely manner and avoid excessive loosening of the rock mass. Detailed geotechnical monitoring and continuous assessment of the observed system behaviour are crucial. This article discusses positive and negative experiences and describes measurement methods and procedures with the aim of successfully utilising yielding elements.

Authors

Institutions

Publication Details

Journal
Geomechanics and Tunnelling
Published
2026-04-01
DOI
https://doi.org/10.1002/geot.70094
Primary Topic
Tunneling and Rock Mechanics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

SBT – Experiences with tunnel support using yielding elements at construction lot SBT2.1

Alexander Poisel, Robert Vaněk, Alexander Meier, Lukas Wagner
Geomechanics and Tunnelling
Tunneling and Rock Mechanics
article

SBT – Experiences with tunnel support using yielding elements at construction lot SBT2.1

Alexander Poisel, Robert Vaněk, Alexander Meier, Lukas Wagner
article en

Abstract

Abstract The use of yielding elements is a highly effective method in deep rock tunnel construction for protecting the shotcrete, particularly in the early stages, from excessive stress caused by high rock loads. Installing multiple rows of yielding elements results in a ductile and flexible support. By deliberately allowing additional deformations, stresses are transferred into deeper rock regions in accordance with the NATM philosophy. Consequently, the stress‐strain relationship of the yielding elements must be adapted to the time‐dependent properties of the shotcrete in relation to the excavation rate. Experience at the SBT2.1 construction site has shown that, when using yielding elements, not only the precise location of the elements within the circumference but also their positioning within the cross‐section is key to success. It is also essential to determine the correct timing for closing the yielding elements in order to achieve a load‐bearing ring closure in a timely manner and avoid excessive loosening of the rock mass. Detailed geotechnical monitoring and continuous assessment of the observed system behaviour are crucial. This article discusses positive and negative experiences and describes measurement methods and procedures with the aim of successfully utilising yielding elements.

Geomechanics and TunnellingVol. 19(2)
Management Center Innsbruck (AT), Shanghai Tunnel Engineering (China) (CN), BEST - Bioenergy and Sustainable Technologies (Austria) (AT), IC Consulenten Ziviltechniker (Austria) (AT)
Sustainable cities and communities
Openalex Percentile: Top 19%
Tunneling and Rock Mechanics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.