Automated Project Rescheduling with Preemptive Activity Splitting for Baseline Restoration

This paper introduces an automated project scheduling framework tailored to the complexities of construction environments, with a particular emphasis on preemptive activity splitting. The proposed method builds on the preemptive multi-mode resource-constrained project scheduling problem formulation and integrates systems thinking with scenario-based optimization to support dynamic rescheduling decisions. By enabling activities to be interrupted and resumed across alternative modes, the framework better captures real-world project execution dynamics compared to conventional deterministic methods. Weekly baseline plans serve as reference points to guide a rolling-horizon rescheduling process that aims to minimize execution deviations while maintaining cost efficiency. Applied to a mechanical system installation case, the framework achieves a 17.57% reduction in recovery cost relative to conventional compression methods, demonstrating improved adaptability and reduced reliance on extensive input data. These results demonstrate the approach’s strong adaptability and its practical potential for construction planning systems, particularly in volatile project environments.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2026-04-07
DOI
https://doi.org/10.1061/jcemd4.coeng-17332
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Automated Project Rescheduling with Preemptive Activity Splitting for Baseline Restoration

Sara Safikhan, Mohsen Sartipipour, Ali Shafaat
Journal of Construction Engineering and Management
Resource-Constrained Project Scheduling
article

Automated Project Rescheduling with Preemptive Activity Splitting for Baseline Restoration

Sara Safikhan, Mohsen Sartipipour, Ali Shafaat
article en

Abstract

This paper introduces an automated project scheduling framework tailored to the complexities of construction environments, with a particular emphasis on preemptive activity splitting. The proposed method builds on the preemptive multi-mode resource-constrained project scheduling problem formulation and integrates systems thinking with scenario-based optimization to support dynamic rescheduling decisions. By enabling activities to be interrupted and resumed across alternative modes, the framework better captures real-world project execution dynamics compared to conventional deterministic methods. Weekly baseline plans serve as reference points to guide a rolling-horizon rescheduling process that aims to minimize execution deviations while maintaining cost efficiency. Applied to a mechanical system installation case, the framework achieves a 17.57% reduction in recovery cost relative to conventional compression methods, demonstrating improved adaptability and reduced reliance on extensive input data. These results demonstrate the approach’s strong adaptability and its practical potential for construction planning systems, particularly in volatile project environments.

Journal of Construction Engineering and ManagementVol. 152(6)
Shahid Beheshti University (IR)
Openalex Percentile: Top 19%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Automated Project Rescheduling with Preemptive Activity Splitting for Baseline Restoration — Sara Safikhan, Mohsen Sartipipour, et al. · Journal of Construction Engineering and Management (2026) | TGRS Research Map | TGRS