An Integrated BIM–NLP Framework for Design-Informed Automated Construction Schedule Generation

Artificial intelligence has attracted increasing attention in the construction industry; however, automated time scheduling remains limited in practical applications. Schedule development remains manual, requiring planners to analyze project documents, define activities, estimate durations, and identify relationships based on logical sequence. This process primarily depends on individual experience and skills, making it both time-consuming and prone to human error. From an engineering design perspective, delayed or inconsistent schedule development weakens design-to-construction feedback, limiting the ability to evaluate constructability and time implications of alternative design decisions during early-stage planning. This study proposes an integrated BIM–Natural Language Processing (NLP) framework to automate activity identification, duration estimation, and logical sequencing for construction scheduling. The framework extracts project data from Revit, organizes it into a bill of quantities format, and then generates an activity list, each activity with a unique ID. Using Sentence-BERT (SBERT) embeddings, the framework estimates activity durations based on semantic similarity. The same semantic process is combined with rule-based reasoning to identify logical relationships, including sequences, supported by an Excel-based reference dictionary that includes logical relationships, productivity, and ID structure. Finally, the framework incorporates a crashing module that proportionally adjusts the duration of activities on the longest path to target the project’s completion time without violating relationships. The proposed framework was validated using real construction project data and produced reliable results. By producing a tool-ready schedule directly from design-model information, the proposed workflow enables earlier schedule feedback loops and supports design-informed planning by allowing designers and planners to assess the time consequences of model-driven scope changes. The results demonstrate that integrating BIM and NLP can transform conventional schedules into faster, more consistent processes, thereby supporting the construction industry.

Authors

Institutions

Publication Details

Journal
Designs
Published
2026-04-07
DOI
https://doi.org/10.3390/designs10020043
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An Integrated BIM–NLP Framework for Design-Informed Automated Construction Schedule Generation

Mahmoud Donia, Hossam Wefki, Ahmed Elhakeem, Emad Elbeltagi
Designs
BIM and Construction Integration
article

An Integrated BIM–NLP Framework for Design-Informed Automated Construction Schedule Generation

Mahmoud Donia, Hossam Wefki, Ahmed Elhakeem, Emad Elbeltagi
article en

Abstract

Artificial intelligence has attracted increasing attention in the construction industry; however, automated time scheduling remains limited in practical applications. Schedule development remains manual, requiring planners to analyze project documents, define activities, estimate durations, and identify relationships based on logical sequence. This process primarily depends on individual experience and skills, making it both time-consuming and prone to human error. From an engineering design perspective, delayed or inconsistent schedule development weakens design-to-construction feedback, limiting the ability to evaluate constructability and time implications of alternative design decisions during early-stage planning. This study proposes an integrated BIM–Natural Language Processing (NLP) framework to automate activity identification, duration estimation, and logical sequencing for construction scheduling. The framework extracts project data from Revit, organizes it into a bill of quantities format, and then generates an activity list, each activity with a unique ID. Using Sentence-BERT (SBERT) embeddings, the framework estimates activity durations based on semantic similarity. The same semantic process is combined with rule-based reasoning to identify logical relationships, including sequences, supported by an Excel-based reference dictionary that includes logical relationships, productivity, and ID structure. Finally, the framework incorporates a crashing module that proportionally adjusts the duration of activities on the longest path to target the project’s completion time without violating relationships. The proposed framework was validated using real construction project data and produced reliable results. By producing a tool-ready schedule directly from design-model information, the proposed workflow enables earlier schedule feedback loops and supports design-informed planning by allowing designers and planners to assess the time consequences of model-driven scope changes. The results demonstrate that integrating BIM and NLP can transform conventional schedules into faster, more consistent processes, thereby supporting the construction industry.

DesignsVol. 10(2)
Mansoura University (EG), Arab Academy for Science, Technology, and Maritime Transport (EG), Egyptian Consulting & Trading Co. Ltd (EG), Port Said University (EG)
Industry, innovation and infrastructure
Openalex Percentile: Top 31%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.