Agent-based simulation for multi-resource-constrained scheduling of scattered atypical repetitive projects

Conventional planning tools struggle to manage the logistical complexity of scattered, short-duration atypical repetitive projects. Although simulation-based planning is well documented, its practical adoption in construction remains limited. This study proposes a simulation-optimization framework implemented in AnyLogic that integrates GIS-enabled agent-based modeling, stochastic simulation, and a GA-based optimization experiment to enable exploration of multi-resource-constrained scheduling decisions. Conceptually informed by multi-mode resource-constrained time-cost trade-off and multiple traveling-salesman formulations, the framework explores makespan-oriented resource-allocation and sequencing configurations under capacity, readiness, and spatial feasibility constraints. Key components include: (i) an adaptive scheduling algorithm for dispersed sites, (ii) a distance-aware rule-based assignment heuristic that supports continuity while limiting avoidable travel, (iii) stochastic disruption modeling, and (iv) spatially explicit visualizations to aid managerial interpretation. Applied to a real-world telecom megaproject, the framework consistently generated substantially shorter schedules across stochastic replications, achieving 46.25% reduction in project duration relative to the practitioner's baseline heuristic plan. Travel time/share, crew idle time, and utilization were recorded as emergent performance metrics and were used to evaluate operational behavior alongside makespan. Limitations include the absence of real-time traffic data, explicit cost modeling, and distance-penalty functions. Future work will incorporate economic and distance-based constraints and broaden comparative evaluation against alternative scheduling approaches.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2026-04-03
DOI
https://doi.org/10.1038/s41598-026-42832-1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Agent-based simulation for multi-resource-constrained scheduling of scattered atypical repetitive projects

Yasmeen A. S. Essawy, Khaled Hamdy, Rawan Abdelrahman Sultan
Scientific Reports
BIM and Construction Integration
article

Agent-based simulation for multi-resource-constrained scheduling of scattered atypical repetitive projects

Yasmeen A. S. Essawy, Khaled Hamdy, Rawan Abdelrahman Sultan
article en

Abstract

Conventional planning tools struggle to manage the logistical complexity of scattered, short-duration atypical repetitive projects. Although simulation-based planning is well documented, its practical adoption in construction remains limited. This study proposes a simulation-optimization framework implemented in AnyLogic that integrates GIS-enabled agent-based modeling, stochastic simulation, and a GA-based optimization experiment to enable exploration of multi-resource-constrained scheduling decisions. Conceptually informed by multi-mode resource-constrained time-cost trade-off and multiple traveling-salesman formulations, the framework explores makespan-oriented resource-allocation and sequencing configurations under capacity, readiness, and spatial feasibility constraints. Key components include: (i) an adaptive scheduling algorithm for dispersed sites, (ii) a distance-aware rule-based assignment heuristic that supports continuity while limiting avoidable travel, (iii) stochastic disruption modeling, and (iv) spatially explicit visualizations to aid managerial interpretation. Applied to a real-world telecom megaproject, the framework consistently generated substantially shorter schedules across stochastic replications, achieving 46.25% reduction in project duration relative to the practitioner's baseline heuristic plan. Travel time/share, crew idle time, and utilization were recorded as emergent performance metrics and were used to evaluate operational behavior alongside makespan. Limitations include the absence of real-time traffic data, explicit cost modeling, and distance-penalty functions. Future work will incorporate economic and distance-based constraints and broaden comparative evaluation against alternative scheduling approaches.

Scientific ReportsVol. 16(1)
Ain Shams University (EG), American University in Cairo (EG)
Ain Shams University
Openalex Percentile: Top 33%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Agent-based simulation for multi-resource-constrained scheduling of scattered atypical repetitive projects — Yasmeen A. S. Essawy, Khaled Hamdy, et al. · Scientific Reports (2026) | TGRS Research Map | TGRS