Removal and installation plans for the SOLEIL II upgrade

The SOLEIL synchrotron, which has been open to the scientific community since 2008, will benefit from an upgrade aimed at improving the brilliance, coherence, and flux of the X-ray beam delivered. This will make it possible to follow biological processes or the functioning of devices operating at sub-millisecond timescales at nanometric resolution, while sharply reducing the detection limit for trace elements. The accelerators (booster and storage ring) will be completely renewed, while the existing tunnels. In addition, six beamlines will be relocated to other places in the experiment hall. A 24-month "dark period" is planned to bring the SOLEIL II program to a successful conclusion. This article presents the strategic plans being developed for dismantling the current accelerators, installing the upgraded components of the new accelerators (girders, magnets, vacuum chambers, electrical and fluid servitudes), and move the six beamlines (radiation protection hutchs and equipments). Prioritizing a cost-effective and time-efficient approach, we began planning by focusing on optimizing spaces and equipment movements necessary for the upgrade process.

Authors

Publication Details

Journal
JACOW
Published
2026-04-02
DOI
https://doi.org/10.18429/jacow-medsi2025-wep71
Primary Topic
Particle Accelerators and Free-Electron Lasers
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Removal and installation plans for the SOLEIL II upgrade

Alexandre Carcy, Nicolas Béchu, Carlos De Oliveira, Gil Baranton et al.
JACOW
Particle Accelerators and Free-Electron Lasers
article

Removal and installation plans for the SOLEIL II upgrade

Alexandre Carcy, Nicolas Béchu, Carlos De Oliveira, Gil Baranton, François Trias
article en

Abstract

The SOLEIL synchrotron, which has been open to the scientific community since 2008, will benefit from an upgrade aimed at improving the brilliance, coherence, and flux of the X-ray beam delivered. This will make it possible to follow biological processes or the functioning of devices operating at sub-millisecond timescales at nanometric resolution, while sharply reducing the detection limit for trace elements. The accelerators (booster and storage ring) will be completely renewed, while the existing tunnels. In addition, six beamlines will be relocated to other places in the experiment hall. A 24-month "dark period" is planned to bring the SOLEIL II program to a successful conclusion. This article presents the strategic plans being developed for dismantling the current accelerators, installing the upgraded components of the new accelerators (girders, magnets, vacuum chambers, electrical and fluid servitudes), and move the six beamlines (radiation protection hutchs and equipments). Prioritizing a cost-effective and time-efficient approach, we began planning by focusing on optimizing spaces and equipment movements necessary for the upgrade process.

JACOW
Openalex Percentile: Top 6%
Particle Accelerators and Free-Electron Lasers
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Removal and installation plans for the SOLEIL II upgrade — Alexandre Carcy, Nicolas Béchu, et al. · JACOW (2026) | TGRS Research Map | TGRS