Scalable data centers – Power generation and delivery challenges and solutions

The exponential growth of data centers, driven by artificial intelligence and large language model research, demands innovative and scalable power delivery architectures to meet escalating energy needs. Traditional grid infrastructure has proven to struggle to keep pace with the rapid deployment and scalability requirements of modern data centers, where big facilities may consume upwards of 1 – 2 GW. In the U.S., building a data center typically takes 18–36 months; however, with the growing interconnection queue and massive processing backlogs, powering an actual data center from the electric grid may often require 4 – 5 + years. To address this challenge, scalable transmission switchyards and on-site power generation solutions are critical. Scalable switchyards enable phased expansion, allowing data centers to incrementally increase power capacity without costly overhauls. Meanwhile, partial or fully on-site generation, such as standalone natural gas generators or natural gas generators complemented with solar PV and battery storage provides resilient, low-latency power while reducing reliance on constrained grid infrastructure. These solutions not only support rapid deployment but also enhance energy efficiency and sustainability, aligning with global decarbonization goals. Through a combination of strategies such as phased expansion, hybrid power delivery through the power grid and on-site battery energy systems, and fully on-site generation, data centers operators can achieve flexibility, reduce downtime, and meet the growing demands of digital transformation. This paper provides an in-depth treatment into the technical engineering design aspects of these architectures, emphasizing their role in enabling the next generation of high-performance, energy-efficient data centers from a power generation and delivery standpoint.

Authors

Institutions

Publication Details

Journal
Energy Reports
Published
2026-03-13
DOI
https://doi.org/10.1016/j.egyr.2026.109178
Primary Topic
Cloud Computing and Resource Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Scalable data centers – Power generation and delivery challenges and solutions

Jaya Damodara, Soham Ghosh
Energy Reports
Cloud Computing and Resource Management
article

Scalable data centers – Power generation and delivery challenges and solutions

Jaya Damodara, Soham Ghosh
article en

Abstract

The exponential growth of data centers, driven by artificial intelligence and large language model research, demands innovative and scalable power delivery architectures to meet escalating energy needs. Traditional grid infrastructure has proven to struggle to keep pace with the rapid deployment and scalability requirements of modern data centers, where big facilities may consume upwards of 1 – 2 GW. In the U.S., building a data center typically takes 18–36 months; however, with the growing interconnection queue and massive processing backlogs, powering an actual data center from the electric grid may often require 4 – 5 + years. To address this challenge, scalable transmission switchyards and on-site power generation solutions are critical. Scalable switchyards enable phased expansion, allowing data centers to incrementally increase power capacity without costly overhauls. Meanwhile, partial or fully on-site generation, such as standalone natural gas generators or natural gas generators complemented with solar PV and battery storage provides resilient, low-latency power while reducing reliance on constrained grid infrastructure. These solutions not only support rapid deployment but also enhance energy efficiency and sustainability, aligning with global decarbonization goals. Through a combination of strategies such as phased expansion, hybrid power delivery through the power grid and on-site battery energy systems, and fully on-site generation, data centers operators can achieve flexibility, reduce downtime, and meet the growing demands of digital transformation. This paper provides an in-depth treatment into the technical engineering design aspects of these architectures, emphasizing their role in enabling the next generation of high-performance, energy-efficient data centers from a power generation and delivery standpoint.

Energy ReportsVol. 15
Black & Veatch (United Kingdom) (GB)
Industry, innovation and infrastructure
Openalex Percentile: Top 40%
Cloud Computing and Resource Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Scalable data centers – Power generation and delivery challenges and solutions — Jaya Damodara, Soham Ghosh · Energy Reports (2026) | TGRS Research Map | TGRS