Modeling the Propagating Effects of Errors and Omissions in Highway Transportation Projects: Methodology and Case Study

Errors and omissions (E&O) are a leading cause of change orders (COs) in transportation infrastructure projects, often resulting in cost overruns, schedule delays, and diminished project outcomes. Although numerous studies have examined the incidence and causes of E&O-related COs, few have systematically modeled their sequential downstream propagation across the construction process. There is a need to investigate how E&Os cascade, leading to additional COs in a project. The objectives of this paper are to (1) identify the patterns of E&O co-occurrence with other CO causes, and (2) propose a methodology to probabilistically model E&O propagation and identify high-risk cost and schedule escalation pathways. This study uses two complementary techniques: association rule mining (ARM) and first-order Markov modeling applied to a case study involving 2,149 highway projects in 2010–2023 at a midwestern Department of Transportation (DOT). Key findings show that projects with early-stage design E&O experience 4.32% higher cost growth and 17.98% longer delays. ARM results reveal strong, nonrandom associations between design-related E&O and downstream COs, such as constructability, utilities, and soils (lift>6.0). Markov modeling identifies design E&O as a high-probability origin state, propagating with typical cost increases of 3%–6% and delays of 12%–24%. Overall, this paper contributes to the integration of CO root-cause analysis with predictive modeling to benefit public infrastructure agencies that seek to enhance their project control policies and practices, especially at the design and constructability stages.

Authors

Institutions

Publication Details

Journal
Journal of Management in Engineering
Published
2026-03-13
DOI
https://doi.org/10.1061/jmenea.meeng-7231
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Modeling the Propagating Effects of Errors and Omissions in Highway Transportation Projects: Methodology and Case Study

Makarand Hastak, Suyash Padhye, Deepak Benny, Samuel Labi
Journal of Management in Engineering
Construction Project Management and Performance
article

Modeling the Propagating Effects of Errors and Omissions in Highway Transportation Projects: Methodology and Case Study

Makarand Hastak, Suyash Padhye, Deepak Benny, Samuel Labi
article en

Abstract

Errors and omissions (E&O) are a leading cause of change orders (COs) in transportation infrastructure projects, often resulting in cost overruns, schedule delays, and diminished project outcomes. Although numerous studies have examined the incidence and causes of E&O-related COs, few have systematically modeled their sequential downstream propagation across the construction process. There is a need to investigate how E&Os cascade, leading to additional COs in a project. The objectives of this paper are to (1) identify the patterns of E&O co-occurrence with other CO causes, and (2) propose a methodology to probabilistically model E&O propagation and identify high-risk cost and schedule escalation pathways. This study uses two complementary techniques: association rule mining (ARM) and first-order Markov modeling applied to a case study involving 2,149 highway projects in 2010–2023 at a midwestern Department of Transportation (DOT). Key findings show that projects with early-stage design E&O experience 4.32% higher cost growth and 17.98% longer delays. ARM results reveal strong, nonrandom associations between design-related E&O and downstream COs, such as constructability, utilities, and soils (lift>6.0). Markov modeling identifies design E&O as a high-probability origin state, propagating with typical cost increases of 3%–6% and delays of 12%–24%. Overall, this paper contributes to the integration of CO root-cause analysis with predictive modeling to benefit public infrastructure agencies that seek to enhance their project control policies and practices, especially at the design and constructability stages.

Journal of Management in EngineeringVol. 42(3)
Purdue University West Lafayette (US)
Industry, innovation and infrastructure
Openalex Percentile: Top 28%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.