A pilot framework for applying earned value analysis to contingency governance in municipal infrastructure projects

Municipalities often discover project overruns too late for effective intervention. This affects the delivery of public works and complicates the financial planning needed for sustainable urban development. Traditional project controls are difficult to apply in this context because they rely on granular cost and schedule data that standard fixed price municipal contracts do not provide. This paper presents a pilot implementation framework that applies Earned Value Analysis (EVA) using data that municipal owners already possess, including contract values, invoices, and certified progress reports. The framework is demonstrated on two municipal infrastructure design projects, treated as case studies rather than a statistical sample. In Project A, an anomalously high Cost Performance Index (CPI) reflected delayed billing relative to certified progress and preceded a major change order. In Project B, a declining Schedule Performance Index (SPI) captured severe delays associated with external regulatory stakeholders and quantified schedule inefficiency as work progressed at less than the planned rate. The study is presented as a proof of concept that shows how contingency can be reframed from a static financial reserve into a structured governance mechanism that links EVA thresholds to predefined management actions. While preliminary and limited to two projects in a single municipality, the framework indicates potential for replication in similar municipal contexts and offers a practical pathway toward more accountable infrastructure delivery.

Authors

Institutions

Publication Details

Journal
Discover Civil Engineering
Published
2026-03-09
DOI
https://doi.org/10.1007/s44290-026-00450-w
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A pilot framework for applying earned value analysis to contingency governance in municipal infrastructure projects

Alence Poudel, Jonathan Braun
Discover Civil Engineering
Construction Project Management and Performance
article

A pilot framework for applying earned value analysis to contingency governance in municipal infrastructure projects

Alence Poudel, Jonathan Braun
article en

Abstract

Municipalities often discover project overruns too late for effective intervention. This affects the delivery of public works and complicates the financial planning needed for sustainable urban development. Traditional project controls are difficult to apply in this context because they rely on granular cost and schedule data that standard fixed price municipal contracts do not provide. This paper presents a pilot implementation framework that applies Earned Value Analysis (EVA) using data that municipal owners already possess, including contract values, invoices, and certified progress reports. The framework is demonstrated on two municipal infrastructure design projects, treated as case studies rather than a statistical sample. In Project A, an anomalously high Cost Performance Index (CPI) reflected delayed billing relative to certified progress and preceded a major change order. In Project B, a declining Schedule Performance Index (SPI) captured severe delays associated with external regulatory stakeholders and quantified schedule inefficiency as work progressed at less than the planned rate. The study is presented as a proof of concept that shows how contingency can be reframed from a static financial reserve into a structured governance mechanism that links EVA thresholds to predefined management actions. While preliminary and limited to two projects in a single municipality, the framework indicates potential for replication in similar municipal contexts and offers a practical pathway toward more accountable infrastructure delivery.

Discover Civil EngineeringVol. 3(1)
Houston Methodist Sugar Land Hospital (US)
Sustainable cities and communities
Openalex Percentile: Top 35%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A pilot framework for applying earned value analysis to contingency governance in municipal infrastructure projects — Alence Poudel, Jonathan Braun · Discover Civil Engineering (2026) | TGRS Research Map | TGRS