Single-Machine Lot Scheduling with Order Rejection

This study investigates the single-machine lot scheduling problem with order rejection. Each order may either be entirely processed in a single lot, or split into two segments to be processed in two consecutive lots. The aim is to construct a feasible schedule that minimizes the sum of the scheduling criterion of the accepted orders and the total rejection cost of the rejected orders. Two scheduling criteria are considered: the makespan and the total completion time. We analyze the computational complexity of both problems. For the case that the scheduling criterion is the makespan, we present an approximation algorithm with a worst-case performance ratio of [Formula: see text], along with a pseudo-polynomial time dynamic programming algorithm and a fully polynomial-time approximation scheme (FPTAS) for this problem. For the case that the scheduling criterion is the total completion time, we present an efficient pseudo-polynomial time algorithm to solve the problem optimally.

Authors

Institutions

Publication Details

Journal
International Journal of Foundations of Computer Science
Published
2026-03-05
DOI
https://doi.org/10.1142/s0129054126400010
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Single-Machine Lot Scheduling with Order Rejection

Xiaoxuan Cheng, Huiyi Ma, Yuzhong Zhang, Juan Zou
International Journal of Foundations of Computer Science
Scheduling and Optimization Algorithms
article

Single-Machine Lot Scheduling with Order Rejection

Xiaoxuan Cheng, Huiyi Ma, Yuzhong Zhang, Juan Zou
article en

Abstract

This study investigates the single-machine lot scheduling problem with order rejection. Each order may either be entirely processed in a single lot, or split into two segments to be processed in two consecutive lots. The aim is to construct a feasible schedule that minimizes the sum of the scheduling criterion of the accepted orders and the total rejection cost of the rejected orders. Two scheduling criteria are considered: the makespan and the total completion time. We analyze the computational complexity of both problems. For the case that the scheduling criterion is the makespan, we present an approximation algorithm with a worst-case performance ratio of [Formula: see text], along with a pseudo-polynomial time dynamic programming algorithm and a fully polynomial-time approximation scheme (FPTAS) for this problem. For the case that the scheduling criterion is the total completion time, we present an efficient pseudo-polynomial time algorithm to solve the problem optimally.

International Journal of Foundations of Computer Science
Qufu Normal University (CN)
Openalex Percentile: Top 37%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.