Participation of Architect-Engineer in the Life Cycle of Nuclear Power Plant: Tools, Opportunities, and Prospects

The established practice of making a decision on the construction of a new nuclear power plant occurs after the approval of the technical and economic requirements for it, taking into account the need to ensure them during the construction process. It is no secret that the most important indicators of technical and economic requirements, such as capital costs and construction time, are currently not kept for almost all nuclear power plant projects. As a rule, this indicates an insufficiently good elaboration of the project, imperfection of the estimated documentation, and management problems during construction. A distinctive feature of the construction of nuclear power plants in the Russian Federation is that the operating organization is at the same time the customer of the project, taking part in ensuring all stages of the life cycle of the nuclear power plant and bearing responsibility for achieving the technical and economic requirements of the project. In this regard, an urgent task is to provide expert support to the project customer from an expert organization capable of independently assessing the quality of the project and the progress of its implementation. The necessity of support of the technical customer’s activity by an expert organization—architect-engineer—is outlined on the basis of positive experience. Taking into account the world practice of designing, building, and operating engineering-complex and capital-intensive projects, it is necessary for the architect-engineer to substantiate a number of optimization measures on the basis of the use of modern methods (requirements management, application of technical, economic, and mathematical models, development and application of digital models and digital twins of nuclear power plants). The necessity of using decision expertise in managing and quality control of nuclear power plant design and construction is substantiated using a technical and economic model and digital twins for new nuclear power plant projects at all stages of their life cycle.

Authors

Institutions

Publication Details

Journal
Physics of Atomic Nuclei
Published
2025-12-01
DOI
https://doi.org/10.1134/s1063778825100151
Primary Topic
Graphite, nuclear technology, radiation studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Participation of Architect-Engineer in the Life Cycle of Nuclear Power Plant: Tools, Opportunities, and Prospects

O. V. Koltun, S. L. Ivanov, D. V. Yakubov
Physics of Atomic Nuclei
Graphite, nuclear technology, radiation studies
article

Participation of Architect-Engineer in the Life Cycle of Nuclear Power Plant: Tools, Opportunities, and Prospects

O. V. Koltun, S. L. Ivanov, D. V. Yakubov
article en

Abstract

The established practice of making a decision on the construction of a new nuclear power plant occurs after the approval of the technical and economic requirements for it, taking into account the need to ensure them during the construction process. It is no secret that the most important indicators of technical and economic requirements, such as capital costs and construction time, are currently not kept for almost all nuclear power plant projects. As a rule, this indicates an insufficiently good elaboration of the project, imperfection of the estimated documentation, and management problems during construction. A distinctive feature of the construction of nuclear power plants in the Russian Federation is that the operating organization is at the same time the customer of the project, taking part in ensuring all stages of the life cycle of the nuclear power plant and bearing responsibility for achieving the technical and economic requirements of the project. In this regard, an urgent task is to provide expert support to the project customer from an expert organization capable of independently assessing the quality of the project and the progress of its implementation. The necessity of support of the technical customer’s activity by an expert organization—architect-engineer—is outlined on the basis of positive experience. Taking into account the world practice of designing, building, and operating engineering-complex and capital-intensive projects, it is necessary for the architect-engineer to substantiate a number of optimization measures on the basis of the use of modern methods (requirements management, application of technical, economic, and mathematical models, development and application of digital models and digital twins of nuclear power plants). The necessity of using decision expertise in managing and quality control of nuclear power plant design and construction is substantiated using a technical and economic model and digital twins for new nuclear power plant projects at all stages of their life cycle.

Physics of Atomic NucleiVol. 88(12)
All-Russian Scientific Research Institute for Operation of Nuclear Power Plants (RU)
Responsible consumption and production
Openalex Percentile: Top 44%
Graphite, nuclear technology, radiation studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.