Mock-Up Test of Cast-in-Place Tunnel Lining for TBM Method

Segmental tunnel linings represent a conventional method commonly employed in tunnel boring machine (TBM) operations. However, this approach presents notable limitations, including handling challenges and the presence of numerous joints prone to leakage. An alternative method involving cast-in-place tunnel lining was experimentally investigated through a scaled mock-up test conducted at approximately 1:4 scale, with a total length of 0.85 m and 2 m lining diameter. In this setup, two reinforced concrete rings were constructed to simulate the surrounding geological conditions and internal formwork. Fiber-reinforced concrete was then pumped into the annular space between the rings, forming a cast-in-place lining with a thickness of 170 mm. To replicate the thrust force exerted by hydraulic actuators of a TBM, a hydrostatic pressure up to 5 MPa was applied from the front side. The experiment demonstrated a linear compaction of fresh concrete by approximately 3%, greater resistance to compaction in the lower section, and a uniformly well-compacted concrete structure throughout the entire volume.

Authors

Institutions

Publication Details

Journal
Infrastructures
Published
2026-02-27
DOI
https://doi.org/10.3390/infrastructures11030078
Primary Topic
Tunneling and Rock Mechanics
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Mock-Up Test of Cast-in-Place Tunnel Lining for TBM Method

Vít Šmilauer, Rostislav Šulc, Martin Válek, Šárka Pešková et al.
Infrastructures
Tunneling and Rock Mechanics
article

Mock-Up Test of Cast-in-Place Tunnel Lining for TBM Method

Vít Šmilauer, Rostislav Šulc, Martin Válek, Šárka Pešková, Petr Vítek, Pavel Růžička, Pavel Horák
article en

Abstract

Segmental tunnel linings represent a conventional method commonly employed in tunnel boring machine (TBM) operations. However, this approach presents notable limitations, including handling challenges and the presence of numerous joints prone to leakage. An alternative method involving cast-in-place tunnel lining was experimentally investigated through a scaled mock-up test conducted at approximately 1:4 scale, with a total length of 0.85 m and 2 m lining diameter. In this setup, two reinforced concrete rings were constructed to simulate the surrounding geological conditions and internal formwork. Fiber-reinforced concrete was then pumped into the annular space between the rings, forming a cast-in-place lining with a thickness of 170 mm. To replicate the thrust force exerted by hydraulic actuators of a TBM, a hydrostatic pressure up to 5 MPa was applied from the front side. The experiment demonstrated a linear compaction of fresh concrete by approximately 3%, greater resistance to compaction in the lower section, and a uniformly well-compacted concrete structure throughout the entire volume.

InfrastructuresVol. 11(3)
Czech Technical University in Prague (CZ), Hochtief (Czechia) (CZ)
Technology Agency of the Czech Republic
Sustainable cities and communities
Openalex Percentile: Top 42%
Tunneling and Rock Mechanics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.