Lessons Learned from the Commissioning Process of the 3rd Mochovce NPP Unit in Slovakia

The paper is focused on broader considerations regarding the commissioning process of the 3rd Unit of nuclear power plant VVER-440 type in Mochovce (Slovakia). The new nuclear plant built in Europe is getting much more slowly than expected, declared or scheduled. Besides the nuclear power plant in Olkiluoto (Finland) and also Flamanville (France), the 3rd Mochovce Unit has finally been in full operation since 6 November 2024. Nevertheless, the more than 30 years of construction process, which was intermittently stopped and frozen, make this success story exceptional. Lessons learned from commissioning are every time specific for different countries but commissioning of nuclear power plant without presence of general designer, respecting all safety requirements and taking full responsibility for this process is unique. Still, in general, the actual Slovak experiences and knowledge could help optimise new buildings in Europe, including dreams about small modular reactor deployment or the building of other clean and sustainable use of advanced nuclear facilities in the future.

Authors

Institutions

Publication Details

Journal
Journal of Nuclear Engineering
Published
2026-02-26
DOI
https://doi.org/10.3390/jne7010018
Primary Topic
Graphite, nuclear technology, radiation studies
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Lessons Learned from the Commissioning Process of the 3rd Mochovce NPP Unit in Slovakia

Slavomír Bebjak, Jana Šimeg Veterníková, Gabriel Farkaš, Vladimir Slugeň et al.
Journal of Nuclear Engineering
Graphite, nuclear technology, radiation studies
article

Lessons Learned from the Commissioning Process of the 3rd Mochovce NPP Unit in Slovakia

Slavomír Bebjak, Jana Šimeg Veterníková, Gabriel Farkaš, Vladimir Slugeň, Martin Mráz, Peter Andraško
article en

Abstract

The paper is focused on broader considerations regarding the commissioning process of the 3rd Unit of nuclear power plant VVER-440 type in Mochovce (Slovakia). The new nuclear plant built in Europe is getting much more slowly than expected, declared or scheduled. Besides the nuclear power plant in Olkiluoto (Finland) and also Flamanville (France), the 3rd Mochovce Unit has finally been in full operation since 6 November 2024. Nevertheless, the more than 30 years of construction process, which was intermittently stopped and frozen, make this success story exceptional. Lessons learned from commissioning are every time specific for different countries but commissioning of nuclear power plant without presence of general designer, respecting all safety requirements and taking full responsibility for this process is unique. Still, in general, the actual Slovak experiences and knowledge could help optimise new buildings in Europe, including dreams about small modular reactor deployment or the building of other clean and sustainable use of advanced nuclear facilities in the future.

Journal of Nuclear EngineeringVol. 7(1)
Slovak University of Technology in Bratislava (SK), Vuje (Slovakia) (SK), Slovenské Elektrárne (Slovakia) (SK)
European Commission
Industry, innovation and infrastructure
Openalex Percentile: Top 44%
Graphite, nuclear technology, radiation studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.