Universal Model for Performance and Delay Tracking of Linear Construction Schedules

Project delays are pervasive in construction projects, frequently causing significant financial, operational, and contractual challenges for all stakeholders involved. Despite the existence of many delay analysis methods, very few are used in practice due to their limiting assumptions, as well as their overly simplistic (generally network-based) schedule inputs. This paper introduces a universal model to track work performance and project delays in linear construction schedules. The model leverages singularity functions to provide a mathematical quantification and graphical representation of delays, enabling real-time tracking and liability allocation. Capabilities of the model are demonstrated through its application to a series of varied performance scenarios and a representative realistic case study. This work contributes to the body of knowledge by offering a structured representation for delay analysis, capable of handling complex relationships within and between activities in dynamic project environments while facilitating computer calculations.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2026-02-23
DOI
https://doi.org/10.1061/jcemd4.coeng-17184
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Universal Model for Performance and Delay Tracking of Linear Construction Schedules

Pablo Ballesteros‐Pérez, Gunnar Lucko, Polina Olivia Helinski
Journal of Construction Engineering and Management
Resource-Constrained Project Scheduling
article

Universal Model for Performance and Delay Tracking of Linear Construction Schedules

Pablo Ballesteros‐Pérez, Gunnar Lucko, Polina Olivia Helinski
article en

Abstract

Project delays are pervasive in construction projects, frequently causing significant financial, operational, and contractual challenges for all stakeholders involved. Despite the existence of many delay analysis methods, very few are used in practice due to their limiting assumptions, as well as their overly simplistic (generally network-based) schedule inputs. This paper introduces a universal model to track work performance and project delays in linear construction schedules. The model leverages singularity functions to provide a mathematical quantification and graphical representation of delays, enabling real-time tracking and liability allocation. Capabilities of the model are demonstrated through its application to a series of varied performance scenarios and a representative realistic case study. This work contributes to the body of knowledge by offering a structured representation for delay analysis, capable of handling complex relationships within and between activities in dynamic project environments while facilitating computer calculations.

Journal of Construction Engineering and ManagementVol. 152(5)
University of the Potomac (US), Universitat Politècnica de València (ES), Catholic University of America (US)
Openalex Percentile: Top 52%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.