Probabilistic optimization of corrective actions for project deadline adherence in projects with stochastic activity durations

Abstract Project control, as an iterative process crucial for managing project uncertainties, demands continual adaptation throughout the project’s lifespan. Activity duration unpredictability, inherents in project networks, poses challenges to meeting deadlines. In response, project managers collect real-time data and employ corrective actions to ensure timely and budget-compliant project delivery. Despite extensive research on project control methodologies, explicit methods for determining the optimal size of corrective actions in stochastic environments have received limited attention. This study addresses this gap by integrating probabilistic optimization models into project control strategies, emphasizing the minimization of corrective action costs. The model ensures that a specified percentile of the project duration distribution aligns with a predefined deadline, offering a probability of meeting the promised project duration. Two control strategies are proposed: preventive, involving a one-time optimization before project initiation, and protective, with continuous re-optimization at specific tracking periods during project execution. Computational experiments on artificial datasets reveal that protective strategies outperform preventive strategies, showing faster convergence and reduced variability in project duration distribution. Results indicate that, on average, a minimum of 6 re-optimizations during project execution is required to minimize both the cumulative cost of corrective actions and the average deviations between project duration realizations and the promised deadline.

Authors

Institutions

Publication Details

Journal
Annals of Operations Research
Published
2026-02-17
DOI
https://doi.org/10.1007/s10479-026-07093-1
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Probabilistic optimization of corrective actions for project deadline adherence in projects with stochastic activity durations

Forough Vaseghi, Mario Vanhoucke
Annals of Operations Research
Resource-Constrained Project Scheduling
article

Probabilistic optimization of corrective actions for project deadline adherence in projects with stochastic activity durations

Forough Vaseghi, Mario Vanhoucke
article en

Abstract

Abstract Project control, as an iterative process crucial for managing project uncertainties, demands continual adaptation throughout the project’s lifespan. Activity duration unpredictability, inherents in project networks, poses challenges to meeting deadlines. In response, project managers collect real-time data and employ corrective actions to ensure timely and budget-compliant project delivery. Despite extensive research on project control methodologies, explicit methods for determining the optimal size of corrective actions in stochastic environments have received limited attention. This study addresses this gap by integrating probabilistic optimization models into project control strategies, emphasizing the minimization of corrective action costs. The model ensures that a specified percentile of the project duration distribution aligns with a predefined deadline, offering a probability of meeting the promised project duration. Two control strategies are proposed: preventive, involving a one-time optimization before project initiation, and protective, with continuous re-optimization at specific tracking periods during project execution. Computational experiments on artificial datasets reveal that protective strategies outperform preventive strategies, showing faster convergence and reduced variability in project duration distribution. Results indicate that, on average, a minimum of 6 re-optimizations during project execution is required to minimize both the cumulative cost of corrective actions and the average deviations between project duration realizations and the promised deadline.

Annals of Operations Research
Ghent University (BE), The London College (GB), Vlerick Business School (BE), University College London (GB)
Openalex Percentile: Top 58%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.