Base position sequence planning for construction robots using bilevel cost optimization

Purpose This paper aims to introduce an integrated planning method for the base position (BP) selection and its optimal visiting sequence for mobile manipulators executing large-scale construction tasks. The method ensures the overall optimality of the planning results through a bilevel coupled optimization of navigation cost and manipulation cost. Design/methodology/approach A two-stage methodology is proposed. First, candidate BP clusters are generated by explicitly incorporating construction process constraints (e.g. layered assembly and staggered patterns). Second, the BP sequence planning is formally modeled as an improved Generalized Traveling Salesman Problem (IGTSP), which is solved using a bilevel cost function that integrates and minimizes both navigation cost (mobile platform path length) and manipulation cost (robotic arm end-effector path length). Findings Experimental evaluations confirmed that by introducing construction constraints, the method achieved significantly higher BP cluster robustness across different layers (with improvements exceeding 14%). Furthermore, compared to state-of-the-art methods, the proposed IGTSP approach successfully reduced the total comprehensive cost by more than 8%, thereby achieving a more efficient and feasible construction sequence and ensuring the smooth completion of on-site tasks. Originality/value This research introduces a process-aware, coupled optimization framework that overcomes the sub-optimality inherent in decoupled BP planning. The novelty lies in the explicit integration of construction process constraints during the BP cluster generation and the formulation of the IGTSP with a bilevel navigation-manipulation cost function, providing a significant advancement toward safe, highly efficient and automated large-scale construction robotics.

Authors

Institutions

Publication Details

Journal
Industrial Robot the international journal of robotics research and application
Published
2026-02-13
DOI
https://doi.org/10.1108/ir-10-2025-0378
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Base position sequence planning for construction robots using bilevel cost optimization

Mengmeng Zhu, P. Zhang, Hao Duan, Shuai Guo
Industrial Robot the international journal of robotics research and application
BIM and Construction Integration
article

Base position sequence planning for construction robots using bilevel cost optimization

Mengmeng Zhu, P. Zhang, Hao Duan, Shuai Guo
article en

Abstract

Purpose This paper aims to introduce an integrated planning method for the base position (BP) selection and its optimal visiting sequence for mobile manipulators executing large-scale construction tasks. The method ensures the overall optimality of the planning results through a bilevel coupled optimization of navigation cost and manipulation cost. Design/methodology/approach A two-stage methodology is proposed. First, candidate BP clusters are generated by explicitly incorporating construction process constraints (e.g. layered assembly and staggered patterns). Second, the BP sequence planning is formally modeled as an improved Generalized Traveling Salesman Problem (IGTSP), which is solved using a bilevel cost function that integrates and minimizes both navigation cost (mobile platform path length) and manipulation cost (robotic arm end-effector path length). Findings Experimental evaluations confirmed that by introducing construction constraints, the method achieved significantly higher BP cluster robustness across different layers (with improvements exceeding 14%). Furthermore, compared to state-of-the-art methods, the proposed IGTSP approach successfully reduced the total comprehensive cost by more than 8%, thereby achieving a more efficient and feasible construction sequence and ensuring the smooth completion of on-site tasks. Originality/value This research introduces a process-aware, coupled optimization framework that overcomes the sub-optimality inherent in decoupled BP planning. The novelty lies in the explicit integration of construction process constraints during the BP cluster generation and the formulation of the IGTSP with a bilevel navigation-manipulation cost function, providing a significant advancement toward safe, highly efficient and automated large-scale construction robotics.

Industrial Robot the international journal of robotics research and application
Shanghai University (CN), Shanghai University of Engineering Science (CN)
Openalex Percentile: Top 56%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.