Visual Evaluation of Construction Schedule Progress by Linking Photographs and 4D Model

During the construction period, numerous site photographs are routinely captured; however, their use is largely limited to simple visual inspection of construction status. To enhance the practical utilization of such photographic information, this study proposes a 4D-based construction progress management system that visually evaluates schedule progress by integrating site photographs within a BIM-based information management framework. The proposed system synchronizes site photographs with corresponding 4D model images using coordinate linkage and applies deep learning–based object detection to identify matching construction elements. Construction progress is approximately estimated by analyzing bounding box overlap between detected elements in site photographs and planned elements in 4D model images. A case study conducted on a bridge construction project demonstrated that the trained model achieved an overall [email protected] of 0.532, and that the proposed method enables intuitive and approximate progress evaluation. The results indicate that the proposed system can improve the usability of site photographs as supporting information for 4D-based construction progress management.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-02-11
DOI
https://doi.org/10.3390/buildings16040733
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Visual Evaluation of Construction Schedule Progress by Linking Photographs and 4D Model

Leen-Seok Kang, Sang-Mi Park
Buildings
BIM and Construction Integration
article

Visual Evaluation of Construction Schedule Progress by Linking Photographs and 4D Model

Leen-Seok Kang, Sang-Mi Park
article en

Abstract

During the construction period, numerous site photographs are routinely captured; however, their use is largely limited to simple visual inspection of construction status. To enhance the practical utilization of such photographic information, this study proposes a 4D-based construction progress management system that visually evaluates schedule progress by integrating site photographs within a BIM-based information management framework. The proposed system synchronizes site photographs with corresponding 4D model images using coordinate linkage and applies deep learning–based object detection to identify matching construction elements. Construction progress is approximately estimated by analyzing bounding box overlap between detected elements in site photographs and planned elements in 4D model images. A case study conducted on a bridge construction project demonstrated that the trained model achieved an overall [email protected] of 0.532, and that the proposed method enables intuitive and approximate progress evaluation. The results indicate that the proposed system can improve the usability of site photographs as supporting information for 4D-based construction progress management.

BuildingsVol. 16(4)
Gyeongsang National University (KR), Korea Electric Power Corporation (South Korea) (KR)
Sustainable cities and communities
Openalex Percentile: Top 57%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.