COMPARATIVE COST ANALYSIS BETWEEN MECHANICAL PLANT AND MANUAL LABOUR IN PUBLIC BUILDING CONSTRUCTION IN ENUGU STATE

This study evaluates the cost-effectiveness of using mechanical plant equipment as an alternative to predominantly manual labour in public building construction across South-East Nigeria. A mixed-methods approach was adopted: quantitative cost and time records were collected from a purposive sample of public building projects and contracting firms in the region, while qualitative data were obtained through semi-structured interviews with project managers, site engineers and labour representatives. Data analysis combined cost-benefit techniques (including cost-effectiveness ratios and payback comparisons), basic inferential statistics, and thematic analysis of interview material. Findings indicate that although initial capital outlays for mechanical plants are higher than for purely manual methods, mechanised operations produced substantial reductions in direct labour costs and project durations, and yielded measurable improvements in workmanship consistency and on-site safety. Over typical project life cycles, mechanisation demonstrated superior cost-effectiveness delivering lower life-cycle costs per unit of output and faster project delivery especially for repetitive, heavy-work activities (earthworks, concrete placement, lifting). Sensitivity analysis showed outcomes are most sensitive to equipment utilization rates and operator availability. The study concludes that strategic adoption of mechanical plants in public building works in South-East Nigeria is economically justified. Recommendations include targeted investment in shared/leased plant fleets, training programmes for operators and managers, procurement rules that incentivise life-cycle costing, and pilot mechanisation policies to scale benefits across the region.

Authors

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-10-29
DOI
https://doi.org/10.5281/zenodo.18609009
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

COMPARATIVE COST ANALYSIS BETWEEN MECHANICAL PLANT AND MANUAL LABOUR IN PUBLIC BUILDING CONSTRUCTION IN ENUGU STATE

Harrison Onyekachi Ugwu
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

COMPARATIVE COST ANALYSIS BETWEEN MECHANICAL PLANT AND MANUAL LABOUR IN PUBLIC BUILDING CONSTRUCTION IN ENUGU STATE

Harrison Onyekachi Ugwu
article en

Abstract

This study evaluates the cost-effectiveness of using mechanical plant equipment as an alternative to predominantly manual labour in public building construction across South-East Nigeria. A mixed-methods approach was adopted: quantitative cost and time records were collected from a purposive sample of public building projects and contracting firms in the region, while qualitative data were obtained through semi-structured interviews with project managers, site engineers and labour representatives. Data analysis combined cost-benefit techniques (including cost-effectiveness ratios and payback comparisons), basic inferential statistics, and thematic analysis of interview material. Findings indicate that although initial capital outlays for mechanical plants are higher than for purely manual methods, mechanised operations produced substantial reductions in direct labour costs and project durations, and yielded measurable improvements in workmanship consistency and on-site safety. Over typical project life cycles, mechanisation demonstrated superior cost-effectiveness delivering lower life-cycle costs per unit of output and faster project delivery especially for repetitive, heavy-work activities (earthworks, concrete placement, lifting). Sensitivity analysis showed outcomes are most sensitive to equipment utilization rates and operator availability. The study concludes that strategic adoption of mechanical plants in public building works in South-East Nigeria is economically justified. Recommendations include targeted investment in shared/leased plant fleets, training programmes for operators and managers, procurement rules that incentivise life-cycle costing, and pilot mechanisation policies to scale benefits across the region.

Zenodo (CERN European Organization for Nuclear Research)
Enugu State University of Science and Technology (NG)
Openalex Percentile: Top 21%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.