The average weight of municipal solid waste disposed of at the Ngipik Landfill was 212.2 tons per day, with 94.8% directly deposited in the landfill. Based on field observation, there was existing reduction carried out by Integrated Waste Processing Facility (Tempat Pengolahan Sampah Terpadu, TPST) before the waste was deposited in the landfill. However, the exact amount of waste that could be reduced at the TPST is unknown. Further research was needed on the amount of waste that can be reduced at TPST. This data could serve as additional information in the waste material flow of Ngipik Landfill. The objectives of this study were to assess the implementation of waste reduction by TPST operational activities, then to do the calculation of waste potential weight and composition that could be reduced by TPST. The weight and composition were measured using direct measurement methods. The potential reduction of the TPST was 7.74 tons per day. The results of the TPST optimization were an increase in the amount of waste entering to 18.8 tons per day with working hours from 7:00 a.m. until 4:00 p.m., the addition of 31 people in the sorting operation, and the expansion of land to 2,521.8 m2.

Authors

Publication Details

Journal
Springer Link (Chiba Institute of Technology)
Published
2026-02-05
DOI
https://doi.org/10.1051/bioconf/202621606009/pdf
Primary Topic
Waste Management and Recycling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimizing Waste Reduction Rate at The Integrated Waste Processing Facility in Ngipik Landfill, Gresik

Deqi Rizkivia Radita, Hanif Ghifari, Susi Agustina Wilujeng
Springer Link (Chiba Institute of Technology)
Waste Management and Recycling
article

Optimizing Waste Reduction Rate at The Integrated Waste Processing Facility in Ngipik Landfill, Gresik

Deqi Rizkivia Radita, Hanif Ghifari, Susi Agustina Wilujeng
article en

Abstract

The average weight of municipal solid waste disposed of at the Ngipik Landfill was 212.2 tons per day, with 94.8% directly deposited in the landfill. Based on field observation, there was existing reduction carried out by Integrated Waste Processing Facility (Tempat Pengolahan Sampah Terpadu, TPST) before the waste was deposited in the landfill. However, the exact amount of waste that could be reduced at the TPST is unknown. Further research was needed on the amount of waste that can be reduced at TPST. This data could serve as additional information in the waste material flow of Ngipik Landfill. The objectives of this study were to assess the implementation of waste reduction by TPST operational activities, then to do the calculation of waste potential weight and composition that could be reduced by TPST. The weight and composition were measured using direct measurement methods. The potential reduction of the TPST was 7.74 tons per day. The results of the TPST optimization were an increase in the amount of waste entering to 18.8 tons per day with working hours from 7:00 a.m. until 4:00 p.m., the addition of 31 people in the sorting operation, and the expansion of land to 2,521.8 m2.

Springer Link (Chiba Institute of Technology)
Openalex Percentile: Top 61%
Waste Management and Recycling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.