Evaluating internal risks of slow disbursement in Vietnam’s state-funded construction projects: a fuzzy multi-criteria approach

Purpose In Vietnam, delays in disbursement for state-funded construction projects remain a persistent challenge, directly impacting stakeholder performance. This study aims to identify significant risks contributing to these delays and proposes a multi-criteria model to mitigate them. Design/methodology/approach Adopting a hybrid method that integrates literature review and expert surveys, the study identifies 17 risk factors grouped into three categories: human-related, policy-related and performance-related. Data was collected through a structured questionnaire and analyzed using Cronbach’s alpha, mean score analysis, Spearman’s rank correlation, Exploratory Factor Analysis and Fuzzy Synthetic Evaluation (FSE). Findings The analysis highlights the limited authority of investors, frequent legal policy changes and delays in site clearance as the most critical causes of slow disbursement. Human-related risks were found to have the greatest influence on this disbursement. Respondents with similar work experience shared consistent assessments, while those in different roles or positions showed divergent views. The FSE results confirm that these risks significantly hamper the disbursement process in public construction projects. Research limitations/implications Evaluating disbursement delays and developing a corresponding model are essential for future research on enhancing project performance. Nevertheless, further in-depth study is needed to understand the full impact of these delays. Practical implications Stakeholders should prioritize improving the qualifications and authority of staff and managers involved in the disbursement process. Doing so will accelerate payment procedures and contribute to more stable cash flow for all parties, especially contractors. Originality/value The study’s findings provide valuable insights for stakeholders, particularly contractors, to manage financial planning better in the face of disbursement delays.

Authors

Institutions

Publication Details

Journal
Journal of Financial Management of Property and Construction
Published
2026-02-05
DOI
https://doi.org/10.1108/jfmpc-10-2024-0077
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluating internal risks of slow disbursement in Vietnam’s state-funded construction projects: a fuzzy multi-criteria approach

Hà Duy Khánh
Journal of Financial Management of Property and Construction
Construction Project Management and Performance
article

Evaluating internal risks of slow disbursement in Vietnam’s state-funded construction projects: a fuzzy multi-criteria approach

Hà Duy Khánh
article en

Abstract

Purpose In Vietnam, delays in disbursement for state-funded construction projects remain a persistent challenge, directly impacting stakeholder performance. This study aims to identify significant risks contributing to these delays and proposes a multi-criteria model to mitigate them. Design/methodology/approach Adopting a hybrid method that integrates literature review and expert surveys, the study identifies 17 risk factors grouped into three categories: human-related, policy-related and performance-related. Data was collected through a structured questionnaire and analyzed using Cronbach’s alpha, mean score analysis, Spearman’s rank correlation, Exploratory Factor Analysis and Fuzzy Synthetic Evaluation (FSE). Findings The analysis highlights the limited authority of investors, frequent legal policy changes and delays in site clearance as the most critical causes of slow disbursement. Human-related risks were found to have the greatest influence on this disbursement. Respondents with similar work experience shared consistent assessments, while those in different roles or positions showed divergent views. The FSE results confirm that these risks significantly hamper the disbursement process in public construction projects. Research limitations/implications Evaluating disbursement delays and developing a corresponding model are essential for future research on enhancing project performance. Nevertheless, further in-depth study is needed to understand the full impact of these delays. Practical implications Stakeholders should prioritize improving the qualifications and authority of staff and managers involved in the disbursement process. Doing so will accelerate payment procedures and contribute to more stable cash flow for all parties, especially contractors. Originality/value The study’s findings provide valuable insights for stakeholders, particularly contractors, to manage financial planning better in the face of disbursement delays.

Journal of Financial Management of Property and Construction
Ho Chi Minh City University of Technology and Engineering (VN), Ho Chi Minh City University of Technology (VN)
Openalex Percentile: Top 68%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.