Analysis of Supply Chain Risks in Concrete Dam Construction
This study identifies 35 risks related to the supply chain of concrete dams, of which 25 were selected as critical risks using the Delphi method. Risks were categorized into three groups based on their sources including environmental, network and organizational risks. The Failure Mode and Effect Analysis (FMEA) method was then applied to evaluate the significance of risks in three areas of construction cost, time and quality. The results revealed that 44% of risks in the construction cost category were critical, while 21% of risks in construction time and 12% in construction quality were found to be critical. Appropriate responses to mitigate critical risks were provided, including the use of alternative supply resources, rigorous project scheduling, and diversified financial strategies. This study highlights the importance of risk management in improving project performance in terms of cost, time, and quality, and emphasizes the need for effective communication and continuous risk monitoring throughout the project lifecycle.
Authors
- Ali Katebi (ORCID: https://orcid.org/0000-0002-1072-2977)
- Hamed Sarkardeh (ORCID: https://orcid.org/0000-0003-2136-0868)
- Ayda Mirzaahmadi
- Mohammad Mirzaahmadi
Institutions
- Kharazmi University (IR)
- Norwegian University of Science and Technology (NO)
- Norwegian Environment Agency (NO)
- Hakim Sabzevari University (IR)
- NTNU Samfunnsforskning (NO)
Publication Details
- Journal
- SHILAP Revista de lepidopterología
- Published
- 2025-10-01
- DOI
- https://doi.org/10.22055/jhs.2025.48099.1324
- Primary Topic
- Supply Chain Resilience and Risk Management
- Type
- article
- Field-Weighted Citation Impact
- 0.00