A Successful Data Centre Refurbishment Project

Queen Mary University of London (QMUL) has recently finished refurbishing its data centre that house our computing cluster supporting the WLCG project. After 20 years of operation the original data centre had significant cooling issues and increases in energy prices have all driven the need for refurbishment amid growing awareness of climate change.In addition there is a need to increase the capacity (from 150kW) to cope with the expected increased needs to the high luminosity LHC and new astronomy projects such as the LSST and SKA observatories. A summary of the project is presented covering the project time line and solutions implemented (in row cooling, hot aisle containment, heat pumps and dry air coolers). Experiences and lessons learnt in the design, building and use of the data centre (covering choices in power supply, rack density, storage space, floor type, lighting, monitoring, etc. . . ) are discussed. Effects of budget constraints and project rescoping due to inflation are also discussed.

Authors

Publication Details

Journal
Springer Link (Chiba Institute of Technology)
Published
2025-10-07
DOI
https://doi.org/10.1051/epjconf/202533701253/pdf
Primary Topic
Heat Transfer and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Successful Data Centre Refurbishment Project

R.A. Owen, Daohai Li, Dimitrios Toroz, Jonathan Hays et al.
Springer Link (Chiba Institute of Technology)
Heat Transfer and Optimization
article

A Successful Data Centre Refurbishment Project

R.A. Owen, Daohai Li, Dimitrios Toroz, Jonathan Hays, Daniel Traynor
article en

Abstract

Queen Mary University of London (QMUL) has recently finished refurbishing its data centre that house our computing cluster supporting the WLCG project. After 20 years of operation the original data centre had significant cooling issues and increases in energy prices have all driven the need for refurbishment amid growing awareness of climate change.In addition there is a need to increase the capacity (from 150kW) to cope with the expected increased needs to the high luminosity LHC and new astronomy projects such as the LSST and SKA observatories. A summary of the project is presented covering the project time line and solutions implemented (in row cooling, hot aisle containment, heat pumps and dry air coolers). Experiences and lessons learnt in the design, building and use of the data centre (covering choices in power supply, rack density, storage space, floor type, lighting, monitoring, etc. . . ) are discussed. Effects of budget constraints and project rescoping due to inflation are also discussed.

Springer Link (Chiba Institute of Technology)
Climate action
Openalex Percentile: Top 40%
Heat Transfer and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A Successful Data Centre Refurbishment Project — R.A. Owen, Daohai Li, et al. · Springer Link (Chiba Institute of Technology) (2025) | TGRS Research Map | TGRS