Optimizing Task Scheduling for Efficient and Ergonomic Human–Robot Collaboration in Construction Tasks

Human–robot collaboration (HRC) offers transformative potential in construction to mitigate labor shortages and enhance productivity. Effective task scheduling between human workers and robots is essential for maximizing productivity and reducing workloads of human workers. Extensive research focusing on either task sequencing or work–rest scheduling often neglects the interdependence between these two components, leading to suboptimal performance of the overall team. Additionally, the existing literature on task scheduling in HRC scenarios within construction is limited, particularly regarding the integration of the dynamic behavior of human and superior physical capabilities of robots. Research gaps remain in coupling task sequencing and work–rest scheduling, as well as in considering the distinct capabilities of human and robot agents. This study proposes an approach that integrates work–rest scheduling with task sequencing by incorporating rest periods as a special task within the optimization process. The proposed method employs a multiobjective genetic algorithm to maximize work output and robot utilization as well as minimize human fatigue, while considering dynamic worker productivity. Additionally, the framework is designed to reschedule tasks in response to the dynamic behaviors of human workers. Experimental results validate the effectiveness of the proposed method in enhancing productivity and reducing human fatigue. This improvement exceeds 10% when compared to existing studies that separate work–rest scheduling from task sequencing. The dynamic scheduling capabilities in adapting to human flexible actions are also verified in comparison to predefined scheduling.

Institutions

Publication Details

Journal
ASCE OPEN Multidisciplinary Journal of Civil Engineering
Published
2026-02-02
DOI
https://doi.org/10.1061/aomjah.aoeng-0094
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimizing Task Scheduling for Efficient and Ergonomic Human–Robot Collaboration in Construction Tasks

ASCE OPEN Multidisciplinary Journal of Civil Engineering
BIM and Construction Integration
article

Optimizing Task Scheduling for Efficient and Ergonomic Human–Robot Collaboration in Construction Tasks

article en

Abstract

Human–robot collaboration (HRC) offers transformative potential in construction to mitigate labor shortages and enhance productivity. Effective task scheduling between human workers and robots is essential for maximizing productivity and reducing workloads of human workers. Extensive research focusing on either task sequencing or work–rest scheduling often neglects the interdependence between these two components, leading to suboptimal performance of the overall team. Additionally, the existing literature on task scheduling in HRC scenarios within construction is limited, particularly regarding the integration of the dynamic behavior of human and superior physical capabilities of robots. Research gaps remain in coupling task sequencing and work–rest scheduling, as well as in considering the distinct capabilities of human and robot agents. This study proposes an approach that integrates work–rest scheduling with task sequencing by incorporating rest periods as a special task within the optimization process. The proposed method employs a multiobjective genetic algorithm to maximize work output and robot utilization as well as minimize human fatigue, while considering dynamic worker productivity. Additionally, the framework is designed to reschedule tasks in response to the dynamic behaviors of human workers. Experimental results validate the effectiveness of the proposed method in enhancing productivity and reducing human fatigue. This improvement exceeds 10% when compared to existing studies that separate work–rest scheduling from task sequencing. The dynamic scheduling capabilities in adapting to human flexible actions are also verified in comparison to predefined scheduling.

ASCE OPEN Multidisciplinary Journal of Civil EngineeringVol. 4(1)
Hong Kong University of Science and Technology (HK), HKUST Shenzhen Research Institute (CN)
Decent work and economic growth
Openalex Percentile: Top 69%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimizing Task Scheduling for Efficient and Ergonomic Human–Robot Collaboration in Construction Tasks · ASCE OPEN Multidisciplinary Journal of Civil Engineering (2026) | TGRS Research Map | TGRS