Early Settlements of Construction Disputes in Public Projects: An Archetype for Reducing Disagreements over Delay Assessments

This study aims to improve early settlements of construction delay disputes via contract claims procedures. The research method includes the evaluation of twenty-one case studies, academic and grey literature and case law concerning disagreements over delay assessments. The results reveal the two primary root causes of the escalations of such disagreements from contract claims into disputes, including the fact that legal systems do not offer best or good practice guidance on delay analysis methods, and construction agreements infrequently ensure contractual certainty and a clear risk allocation for the measurement and management of delays. The proposed archetype provides (i) a useful analytical framework that enhances the construction and legal professionals’ understanding of dispute causation and (ii) an integrated solution that incorporates contractual and procedural reforms and technological solutions, ensuring the production and distribution of reliable source materials, mechanisms that improve contractual certainty, and a reduction in the data repositories and the professionals currently involved in the assessment of delays.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-02-01
DOI
https://doi.org/10.3390/buildings16030597
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Early Settlements of Construction Disputes in Public Projects: An Archetype for Reducing Disagreements over Delay Assessments

Vasil Angelov Atanasov
Buildings
Construction Project Management and Performance
article

Early Settlements of Construction Disputes in Public Projects: An Archetype for Reducing Disagreements over Delay Assessments

Vasil Angelov Atanasov
article en

Abstract

This study aims to improve early settlements of construction delay disputes via contract claims procedures. The research method includes the evaluation of twenty-one case studies, academic and grey literature and case law concerning disagreements over delay assessments. The results reveal the two primary root causes of the escalations of such disagreements from contract claims into disputes, including the fact that legal systems do not offer best or good practice guidance on delay analysis methods, and construction agreements infrequently ensure contractual certainty and a clear risk allocation for the measurement and management of delays. The proposed archetype provides (i) a useful analytical framework that enhances the construction and legal professionals’ understanding of dispute causation and (ii) an integrated solution that incorporates contractual and procedural reforms and technological solutions, ensuring the production and distribution of reliable source materials, mechanisms that improve contractual certainty, and a reduction in the data repositories and the professionals currently involved in the assessment of delays.

BuildingsVol. 16(3)
Robert Gordon University (GB)
Openalex Percentile: Top 74%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.