Techno-Economic Analysis of Captive Solar Power Systems for Tanzania’s Manufacturing Sector: Barriers, Opportunities, and Feasibility

This study provides a comprehensive techno-economic analysis of the barriers, opportunities, and feasibility of adopting captive solar photovoltaic (PV) systems in Tanzania’s industrial manufacturing sector. Despite Tanzania’s high solar irradiation potential, averaging 4.5 to 7.0 kWh/m²/day, the uptake of captive solar systems remains minimal, with only 2.3 percent of surveyed firms currently using solar energy, primarily for non-productive uses such as security lighting. Using a mixed-methods approach, data were collected from 43 manufacturing firms in the Dar es Salaam and Pwani regions through structured questionnaires, supported by PVSyst simulations and financial modelling to assess two system configurations: grid-connected PV systems without battery storage and hybrid PV systems with battery storage. The results demonstrate strong financial viability for the battery-free configuration, which achieved a Levelized Cost of Electricity (LCOE) of 6.39 US¢/kWh, a payback period of 7 years, and a Net Present Value (NPV) of USD 700,019. In contrast, the battery-inclusive system yielded a higher LCOE of 16.12 US¢/kWh, an extended payback period of 23 years, and a total project cost NPV of USD 1.77 million. Sensitivity analysis confirmed project viability across discount rates ranging from 7% to 21%. The system achieved a 23.6% PV penetration relative to the facility’s total electricity demand and is expected to avoid between 3,476 and 8,603 tons of CO₂ annually, depending on the baseline energy source displaced (grid or diesel). Key barriers identified include high upfront capital costs, limited technical expertise, and regulatory uncertainty. However, significant opportunities exist in training, policy reforms, and financial innovation. The study recommends targeted incentives, net metering implementation, and public-private partnerships to accelerate the adoption of industrial-scale captive solar systems, contributing to Tanzania’s transition toward a resilient, low-carbon energy future.

Authors

Publication Details

Journal
Tanzania Journal of Engineering and Technology
Published
2025-12-30
DOI
https://doi.org/10.65085/2619-8789.1075
Primary Topic
Hybrid Renewable Energy Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Techno-Economic Analysis of Captive Solar Power Systems for Tanzania’s Manufacturing Sector: Barriers, Opportunities, and Feasibility

Edson Uhale, Sarah P. Ayeng'o
Tanzania Journal of Engineering and Technology
Hybrid Renewable Energy Systems
article

Techno-Economic Analysis of Captive Solar Power Systems for Tanzania’s Manufacturing Sector: Barriers, Opportunities, and Feasibility

Edson Uhale, Sarah P. Ayeng'o
article en

Abstract

This study provides a comprehensive techno-economic analysis of the barriers, opportunities, and feasibility of adopting captive solar photovoltaic (PV) systems in Tanzania’s industrial manufacturing sector. Despite Tanzania’s high solar irradiation potential, averaging 4.5 to 7.0 kWh/m²/day, the uptake of captive solar systems remains minimal, with only 2.3 percent of surveyed firms currently using solar energy, primarily for non-productive uses such as security lighting. Using a mixed-methods approach, data were collected from 43 manufacturing firms in the Dar es Salaam and Pwani regions through structured questionnaires, supported by PVSyst simulations and financial modelling to assess two system configurations: grid-connected PV systems without battery storage and hybrid PV systems with battery storage. The results demonstrate strong financial viability for the battery-free configuration, which achieved a Levelized Cost of Electricity (LCOE) of 6.39 US¢/kWh, a payback period of 7 years, and a Net Present Value (NPV) of USD 700,019. In contrast, the battery-inclusive system yielded a higher LCOE of 16.12 US¢/kWh, an extended payback period of 23 years, and a total project cost NPV of USD 1.77 million. Sensitivity analysis confirmed project viability across discount rates ranging from 7% to 21%. The system achieved a 23.6% PV penetration relative to the facility’s total electricity demand and is expected to avoid between 3,476 and 8,603 tons of CO₂ annually, depending on the baseline energy source displaced (grid or diesel). Key barriers identified include high upfront capital costs, limited technical expertise, and regulatory uncertainty. However, significant opportunities exist in training, policy reforms, and financial innovation. The study recommends targeted incentives, net metering implementation, and public-private partnerships to accelerate the adoption of industrial-scale captive solar systems, contributing to Tanzania’s transition toward a resilient, low-carbon energy future.

Tanzania Journal of Engineering and TechnologyVol. 44(4)
Openalex Percentile: Top 40%
Hybrid Renewable Energy Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Techno-Economic Analysis of Captive Solar Power Systems for Tanzania’s Manufacturing Sector: Barriers, Opportunities, and Feasibility — Edson Uhale, Sarah P. Ayeng'o · Tanzania Journal of Engineering and Technology (2025) | TGRS Research Map | TGRS