Commissioning of the HEPS

The High Energy Photon Source (HEPS) is the first 4th generation light source and the first high-energy storage ring light source in China, with a beam energy of 6 GeV, a circumference of 1360 m and a natural emittance of a few tens of picometers. As a green-field light source, the HEPS construction started in 2019 and is scheduled to be completed in 2025. Now civil construction, component fabrication and tunnel installation, and beam commissioning of the HEPS has been basically finished. In this report, the accelerator and especially the storage ring commissioning results, and main physics issues faced and corresponding measures during the beam commissioning will be presented.

Authors

Publication Details

Journal
JACOW
Published
2026-01-29
DOI
https://doi.org/10.18429/jacow-napac2025-moyn03
Citations
1
Primary Topic
Particle Accelerators and Free-Electron Lasers
Type
article
Field-Weighted Citation Impact
21.93
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Commissioning of the HEPS

Dongbing Li, Mengyu Su, Yi Wen Jiao, Jianshe Cao et al.
1 citations
JACOW
Particle Accelerators and Free-Electron Lasers
21.93
article

Commissioning of the HEPS

Dongbing Li, Mengyu Su, Yi Wen Jiao, Jianshe Cao, Xiyang Huang, Yongsheng Huang, Haisheng Xu, Wen Kang, Yafeng Wu, YuHui DONG, Facheng Zhao, Zihang Zhao, Yuchen Yang, Liyan Qin, Wei Bao, Xiaohao Cui, Daheng Ji, Jiuqing Wang, Senyu Chen, Yuanyuan Wei, Siyu Lin, Zhe Duan, Fang Yan, Xiaoyu Li, Yuanyuan Guo, Gang Xu, Ping He, Xiaohan Lu, Weimin Pan, Zihao Wang, Yanhua Lu, Jian Li, Hongjuan Zheng, Hongfei Ji, Saike Tian, Nan Li, Cai Meng, Na Wang, Yuzhe Liu, Fancong Zeng, Zhiqiang Li, Chenghui Yu, Jing Zhang, Huamin Qu, Yaliang Zhao, Jingyi Li, Yuemei Peng
article en
1 citations

Abstract

The High Energy Photon Source (HEPS) is the first 4th generation light source and the first high-energy storage ring light source in China, with a beam energy of 6 GeV, a circumference of 1360 m and a natural emittance of a few tens of picometers. As a green-field light source, the HEPS construction started in 2019 and is scheduled to be completed in 2025. Now civil construction, component fabrication and tunnel installation, and beam commissioning of the HEPS has been basically finished. In this report, the accelerator and especially the storage ring commissioning results, and main physics issues faced and corresponding measures during the beam commissioning will be presented.

JACOW
Affordable and clean energy
Openalex Percentile: Top 2%
Particle Accelerators and Free-Electron Lasers
21.93
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Commissioning of the HEPS — Dongbing Li, Mengyu Su, et al. · JACOW (2026) | TGRS Research Map | TGRS